Based on the pole replacement method in the power pipe network
A technology of power pipe network and replacement method, which is applied in the field of electric power construction, can solve problems such as electric pole safety accidents, achieve the effects of protecting safety, reducing the probability of accidents, and solving safety accidents
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0018] Based on the pole replacement method in the power pipeline network, the following steps are included:
[0019] (a) Remove the old poles: add temporary pull wires to the poles on both sides of the adjacent poles to prevent the other straight poles from being tilted due to the weight of the wires after the wires are removed and landed. After the wire is completely in contact with the ground, remove the pull wire, pull out the old pole, clean up the pole pit and prepare for pole assembly;
[0020] (b) new mast erection including setting of ground anchors and connection of hoist tools to ground anchors,
[0021] (1) Ground anchor setting: along the center line of the pole pit, in the opposite direction of traction, at a distance of about 1.5 times the length of the pole from the center of the pole pit, bury the ground anchor to fix the brake and the brake rope formed by the temporary pull wire, at the left and right sides of the pole direction On the side, about 1.5 times ...