Method for calculating initial static balanced state of electrified railway contact network
An electrified railway, balanced state technology, applied in computing, power supply lines, electrical digital data processing, etc., can solve problems such as overall analysis of unfavorable structures
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0064] Embodiment one two-span simple chain suspension catenary
[0065] attached Figure 4 It is a schematic diagram of a two-span catenary link. Among them, the left and right ends of the contact line and load-bearing cable line are fixed, and the two lines and cables on the right side meet the tension value T 1 with T 2 , the span is l k , the locator connects the contact line with a certain slope, the catenary cable can slide in the x direction at the locating point, and the upper end of the locator is fixed by a hinge, f c is the gravity of the clamp at each suspension point, the structure height is h, and the distribution law of the hanging string in the x direction is l sd -l dd -...-l dd -l sd , the number of hanging strings in one span is n d . Attached Figure 5 The catenary is meshed, and the catenary cable and the contact line between the suspension strings are divided into a cable unit, and the suspension strings and locators are regarded as rod units. ...
Embodiment 2
[0082] Embodiment two two-span elastic chain suspension
[0083] attached Image 6 It is a schematic diagram of two spans of an elastic chain suspension catenary. Among them, the left and right ends of the contact line and load-bearing cable line are fixed, and the two lines and cables on the right side meet the tension value T 1 with T 2 , the span is l k , the locator connects the contact line with a certain slope, the catenary cable can slide in the x direction at the locating point, and the upper end of the locator is fixed by a hinge, f c is the gravity of the clamp at each suspension point, the structure height is h, and the distribution law of the hanging string in the x direction is l sd -l dd -...-l dd -l sd , the number of hanging strings in one span is n d , the span of the elastic sling is l s , the sling tension is T s . The specific parameters of the bomb chain catenary in the second embodiment are shown in Table 5.
[0084] Table 5 Catenary parameter...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 