A construction method for comb-tooth groove guide and interception of coastal double-row steel sheet pile cofferdam
A technology of steel sheet pile cofferdam and construction method, applied in sheet pile wall, foundation structure engineering, construction, etc., can solve the problems of long construction period and large investment, reduce construction cost, speed up construction speed, reduce the risk of closure and construction effect of difficulty
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0026] The construction method of comb-tooth groove guide and interception of a coastal double-row steel sheet pile cofferdam of the present invention will be described below in conjunction with the accompanying drawings.
[0027] In the embodiment of the present invention, the overall layout of the double-row steel sheet pile cofferdam is a circular layout, the total length of the cofferdam axis is about 1500m, and the total area of the surrounding foundation pit is about 140,000m 2 . In the interception process of the double-row steel sheet pile cofferdam, a dragon mouth is set, and the length of the dragon mouth is 30m. By setting up the diversion chamber, the inner and outer flow passages of the foundation pit are opened, the water level inside and outside the foundation pit and the water flow velocity of the Helonglongkou are reduced, and the smooth closure of the double-row steel sheet pile cofferdam is effectively guaranteed.
[0028] The concrete construction method...