Construction method for erecting and installing bridge pier top block by adopting floating crane

A construction method and technology for bridge piers, applied in the direction of bridge construction, bridges, erection/assembly of bridges, etc., can solve the problems of high risk, tight time, quality and speed cannot be guaranteed, etc.

Inactive Publication Date: 2016-05-04
CCCC SHEC FIRST HIGHWAY ENG
View PDF5 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The advantage of this erection method is: the pier top block is erected by the bridge erecting machine, which saves costs. The disadvantage is: it is necessary to reserve a trestle bridge to install the triangular truss, and the pier body will be repaired later. After the pier top block is erected and installed, the pier top The pou

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for erecting and installing bridge pier top block by adopting floating crane
  • Construction method for erecting and installing bridge pier top block by adopting floating crane

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0017] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0018] This embodiment discloses a construction method in which the top block of a bridge pier is erected and installed by means of a floating crane. It is an improvement over the shortcomings of using a bridge erecting machine to hoist the top block of a pier in the background technology. It includes the following steps:

[0019] 1) A permanent support 2 is installed on the top of the pier body 1, a temporary support 3 is erected on the side of the pier body 1, and several three-way adjustment jacks 4 are arranged on the top surface of the temporary support 3;

[0020] 2) Reference figure 1 Firstly, the pier top block 5 is lifted above the top of the pier body 1 by floating hoisting. At this time, the vertical and horizontal axes of the pier top block 5 are roughly aligned with the vertical and horizontal axes on the pier top. The bo...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method for erecting and installing a bridge pier top block by adopting a floating crane. The method comprises the steps that a permanent support is installed on the top of a pier body, a temporary support is erected on the side of the pier body, and a three-direction adjusting jack is arranged on the top face of the temporary support; the floating crane is adopted for lifting the pier top block to the portion above the top of the pier body, and the three-direction adjusting jack is controlled to complete positioning of the pier top block; a screw-type jack is arranged on the temporary support, and the floating crane instrument is disassembled; finally, pouring and tamping are performed on a leveling layer between the bottom of the pier top block and the permanent support; after the requirement for strength is met, the three-direction adjusting jack and the screw-type jack are disassembled. The pier top block is erected in a floating-crane mode, a distribution beam is anchored on the pier top block after construction is completed, a bridge machine is erected, and a via hole is formed, so that the trouble caused by installing a bracket reserved branch trestle is omitted, the cost input is reduced, the erection safety of the pier top block is further ensured, and the erection speed of the bridge machine is increased so as to improve the erection safety and stability of the pier top block.

Description

technical field [0001] The invention relates to the technical field of bridge erection construction, in particular to a construction method in which bridge pier top blocks are erected and installed by floating cranes. Background technique [0002] At present, the beam erecting operation method of the segmental assembly walking bridge erecting machine is to prefabricate the box-shaped concrete beams to be erected in the beam yard in advance, and then use the beam truck to transport them to the position of the bridge hole. The erected bridge erecting machine feeds the beam at the rear end, and the crane girder crane on the bridge erecting machine hangs and arranges the prefabricated beam segments sequentially transported one by one under the main girder where the bridge erecting machine has been aligned with the bridge hole. Finally, each beam segment is assembled into a whole beam piece. [0003] The beam outriggers of the bridge erecting machine are usually supported by the...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E01D21/00
CPCE01D21/00
Inventor 毛奎文德安朱晓明吴凯军莫先琳赵军科田新平
Owner CCCC SHEC FIRST HIGHWAY ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products