A technology of bored piles and new technology, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve problems such as damage to the main reinforcement of the pile foundation and pile head concrete, increase construction costs, slow construction speed, etc., and achieve manufacturing costs. Inexpensive, Efficient, Quality Assured

Inactive Publication Date: 2016-05-18
CHINA RAILWAY SHISIJU GROUP CORP
View PDF0 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] The removal of the pile head of the traditional bored pile is to manually peel off the concrete that needs to be removed bit by bit. Since part of the main reinforcement extends into the concrete of the pile head, it is necessary to use equipment to further peel off the concrete around the steel bar, and then use it after all the steel bars are exposed. The hoisting equipment breaks and lifts the pile core (without steel bars). This construction method wastes manpower, increases construction costs, and even damages the main reinforcement of the pile foundation and pile head concrete. The construction speed is slow

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Novel construction technology for removing pile heads of bored piles

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0008] The new technology of bored pile pile head breaking construction, such as figure 1 As shown, the bamboo plywood installed on the inside and outside of the reinforcement cage must be firmly fixed to the main reinforcement to prevent the bamboo plywood from falling off or slipping into the concrete below the pile head. The height of the bamboo plywood set is 90cm, and it cannot go deep into the concrete below the pile head. When lowering the reinforcement cage, it is necessary to accurately calculate the length of the hanging bars to prevent the reinforcement cage from floating or falling.

[0009] Pay attention to the protection of the bamboo plywood during the lowering of the reinforcement cage, the downpipe and other operations to prevent damage to the bamboo plywood and increase the difficulty of pile head removal. After the pile head is broken, ensure that the top of the pile is anchored into the cap by 10cm, that is, the elevation of the pile top should be 10cm hig...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a novel construction technology for removing pile heads of bored piles. Bamboo plywood is arranged on the inner side and the outer side of a reinforcement cage, and must be fixed with main reinforcements firmly, so that the bamboo plywood is prevented from falling or sliding down into concrete of lower parts of the pile heads. Bonding between the concrete of the pile heads and the main reinforcements is avoided, when the pile heads are chiseled off after a foundation pit is excavated, the concrete is not stripped from the reinforcements, so that the chiseling speed of the pile heads is increased greatly, and construction cost is reduced. The novel construction technology for removing the pile heads of the bored piles has convenience and rapidness, namely the new technology is convenient to operate, the number of corollary equipment is small, the new technology is easily accepted by constructors, and the constructors can skillfully operate the new technology rapidly.

Description

technical field [0001] The invention relates to a new construction technology, in particular to a new construction technology for removing the head of a bored pile. Background technique [0002] The removal of the pile head of the traditional bored pile is to manually peel off the concrete that needs to be removed bit by bit. Since part of the main reinforcement extends into the concrete of the pile head, it is necessary to use equipment to further peel off the concrete around the steel bar, and then use it after all the steel bars are exposed. The hoisting equipment breaks and lifts the pile core (without steel bars). This construction method wastes labor, increases construction costs, and even damages the main reinforcement of the pile foundation and pile head concrete, and the construction speed is relatively slow. With the pile foundation construction using the partition method, the concrete at the pile head and the main reinforcement will not be wrapped. After the found...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D9/00
Inventor 丁雨露王应魁
Owner CHINA RAILWAY SHISIJU GROUP CORP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products