Material distribution list generation method and device of current procedure in mold production plan
A technology of production planning and current process, applied in logistics, computing, instruments, etc., can solve the problem that materials cannot be supplied on time, and achieve the effect of ensuring timely supply, reducing inventory, and high practical value
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0037] see figure 1 , is a flow chart of the realization of the method for generating the material distribution list of the current process in the mold production plan of the present invention. As shown in the figure, the method for generating the material distribution list includes the following implementation steps:
[0038] Step S101, read all the processing procedures P(j) of the required resource R(i) in the production plan under the specified time period;
[0039] Step S102, reading the preceding process PreP(i) of each processing process under the resource R(i);
[0040] Step S103, judging whether the pre-process PreP(i) is material preparation;
[0041] Step S104, when the pre-process PreP(i) is material preparation, read the material information corresponding to the pre-process as the pre-material of the current processing process, and add it to the delivery list corresponding to the current process.
[0042] In the specific implementation, the warehouse will distri...
Embodiment 2
[0050] Also, see figure 2 , is an implementation principle block diagram of a device for generating a material distribution list of a current process in a mold production plan provided by the present invention. As shown in the figure, the device for generating a material distribution list includes a processing procedure reading module 10, a pre-process reading module The retrieval module 20, the material preparation query module 30 and the delivery list generation module 40, wherein the processing procedure reading module 10 is suitable for reading all the processing procedures P(j) of the required resource R(i) in the production plan under the specified time period The pre-process reading module 20 is adapted to read the pre-process PreP(i) of each processing procedure under the resource R(i); the material preparation query module 30 is suitable for judging the pre-process PreP(i) Whether it is material preparation; the distribution list generation module 40 is suitable for ...