Method of Installing Tied Rods of Long-span Arch Bridge

A technology for large-span arch bridges and tie rods, which is applied in the erection/assembly of bridges, bridges, and bridge construction, etc., can solve the problems of long occupation of cable cranes, poor lateral overall stability, and difficulty in foundation construction, saving temporary structures. , The construction is convenient and easy to operate, and the effect of saving temporary materials

Active Publication Date: 2019-06-21
CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] However, the gantry crane is only suitable for the installation of small-span arch bridge tie rods, and the installation requires a lot of temporary materials, the foundation construction is difficult, the assembly and installation are time-consuming and laborious, and it occupies the waterway, which affects the construction period
[0004] When using a cable crane to install tie rods, there are many artificial high-altitude operations, the risk factor is large, and it takes a long time to use the cable crane, which affects the construction period
[0005] When catwalk auxiliary tie rods are used for installation, there are many materials in Dalin, the catwalk construction process is complicated, the flexibility is large, and the overall lateral stability is poor, and it affects the construction of the main beam and the hoisting of the cable crane, prolonging the cycle

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method of Installing Tied Rods of Long-span Arch Bridge
  • Method of Installing Tied Rods of Long-span Arch Bridge
  • Method of Installing Tied Rods of Long-span Arch Bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] The present invention will be described in further detail below in conjunction with the accompanying drawings and embodiments.

[0037] The invention provides a method for installing tie rods of a long-span arch bridge, the method comprising the following steps:

[0038] S1. Two main cables 3 arranged side by side are installed on two adjacent first buckle towers 1 and second buckle towers 2, and one end of two vertical temporary supports 4 is arranged on the arch rib 5 respectively, and the other end Temporarily anchored next to the pier of the first buckle tower 1;

[0039] Specifically, the present invention installs two main cables 3 arranged side by side on the distribution beams 10 of two adjacent first buckle towers 1 and second buckle towers 2 . The main cable 3 mainly plays a load-bearing role. Because it is directly anchored at the distribution beam 10 at the bottom of the buckle tower, the temporary structure is greatly saved, that is, the temporary material...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a method for mounting long-span arch bridge tie bars and relates to the field of long-span bridge construction. The method comprises the steps that two main ropes are arrangedon a first buckle tower and a second buckle tower which are adjacent to each other, one end of either vertical temporary support is arranged on an arch rib, and the other end of either vertical temporary support is temporarily anchored nearby a pier of the first buckle tower. Multiple temporary slings are arranged at intervals and connected into an entirety in series by using connection ropes, thetie bars are connected with pulling cables, the pulling cables are used for pulling the tie bars, and the tie bars are placed on all the temporary slings in sequence. The tie bars are continuously pulled till the two vertical temporary supports can be connected with set portions on the tie bars, and one temporarily-anchored end of either vertical temporary support is disassembled and connected with the corresponding tie bar. The tie bars are continuously pulled till one end of each tie bar penetrates through a pipe, and the tie bars are temporarily anchored. The vertical temporary supports are lifted to the designed elevation and locked. According to the method for mounting the long-span arch bridge tie bars, the required temporary materials are few, the sea channel is not occupied, the working period is saved, and the tie bars are convenient to construct.

Description

technical field [0001] The invention relates to the field of long-span bridge construction, in particular to a method for installing tie bars of a long-span arch bridge. Background technique [0002] In the existing arch bridge tie bar construction, the most common method is to complete its installation with the aid of gantry cranes, cable cranes or catwalks. [0003] However, the gantry crane is only suitable for the installation of small-span arch bridge tie rods, and the installation requires a lot of temporary materials, the foundation construction is difficult, the assembly and installation are time-consuming and laborious, and the channel is occupied, which affects the construction period. [0004] When using a cable crane to install the tie rod, there are many artificial high-altitude operations, the risk factor is large, and the cable crane takes a long time, which affects the construction period. [0005] When catwalk auxiliary tie rods are used for installation, t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E01D21/00
CPCE01D21/00
Inventor 张小川杜凤代皓毛玮琦涂满明谢守杰马涛刘翠云何柰韩井东李方峰岳万友邹冠黄根诸洪
Owner CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products