A technology of prefabricated components and construction methods, which is applied to building components, structural elements, building reinforcements, etc., can solve problems such as explosion of warehouses, grouting of grouting sleeves, and leakage of high-strength mortar, so as to achieve simple construction steps and guarantee Connection strength, the effect of ensuring construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0033] see hint figure 1 , the vertical construction node of the prefabricated component in this embodiment 1, including the second prefabricated component 2 located below and the first prefabricated component 1 located above, the bottom side of the first prefabricated component 1 embedded grouting sleeve 3, the grouting sleeve 3 One end is connected to the stress tendon 11 in the first prefabricated component 1, and the other end is provided with a steel bar connection port (not shown in the figure); placed above the second prefabricated element 2.
[0034] see hint figure 2 During installation, the stress ribs 21 on the top side of the second prefabricated component 2 extend into the inside of the reinforcement connection port of the grouting sleeve 3 on the bottom side of the first prefabricated component 1 . An elastic seal is provided on the surface of the first prefabricated component 1 where it contacts the edge of the second prefabricated component 2 , and the elast...
Embodiment 2
[0043] The vertical construction node of the prefabricated component in this embodiment 2 includes the second prefabricated component 2 at the bottom and the first prefabricated component 1 connected with the second prefabricated component 2 at the top, which is structurally different from that in embodiment 1 in:
[0044] 1. The elastic seal in Embodiment 1 is arranged in the space formed by the seam between the first prefabricated component 1 and the second prefabricated component 2, and the outer edge of the elastic seal does not exceed the bottom side edge of the first prefabricated component 1 (see signal figure 2 ), that is, the elastic seal is placed in the joint; while the elastic seal in embodiment 2 is arranged on the outer edge of the bottom side of the first prefabricated component 1, and is not arranged in the joint space of the two prefabricated components (see the illustration Figure 4 ).
[0045] 2. The clip in embodiment 1 includes a steel plate 6 and a fi...