Method for correcting and determining minimum active power of new energy station participating in direct electricity purchase of large users

A technology of active power and determination method, which is applied in the field of correction and determination of minimum active power of new energy stations directly purchased by large users, which can solve the inconvenient control of electric field output, complicated control of dispatchers, and the contract completion rate of new energy stations. Large deviation and other problems, achieve the effect of optimizing the allocation method and reducing the task of section control

Active Publication Date: 2019-12-24
GUIZHOU POWER GRID CO LTD
View PDF10 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] ①Scheduler control is complex
Dispatchers need to complete the distribution of power generation rights in real time based on information such as new energy station installed capacity, load forecasting, and direct purchase transaction contracts, which is extremely inconvenient for power field output control;
[0005] ② It is difficult to guarantee the completion rate of the direct purchase transaction contract
Scheduling generally cannot grasp the power generation of each new energy station in real time, and it is easy to cause the contract completion rate of the new energy station participating in the direct purchase of electricity by large users to deviate greatly from the plan, resulting in the inability to complete the monthly contract transaction electricity;
[0006] ③ It is difficult to guarantee the fairness of the distribution of power generation rights
Since there is no strict and unified distribution standard for power generation rights, it is difficult to guarantee the "three public" scheduling principles

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for correcting and determining minimum active power of new energy station participating in direct electricity purchase of large users
  • Method for correcting and determining minimum active power of new energy station participating in direct electricity purchase of large users
  • Method for correcting and determining minimum active power of new energy station participating in direct electricity purchase of large users

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0046] Example: such as figure 1 As shown, a method for correcting and determining the minimum active power of a new energy station participating in the direct purchase of electricity by a large user, the method for determining the correction includes:

[0047] A. Obtain the cross-section data involved in the direct purchase of electricity by large users;

[0048] B. Calculate the power generation required by the new energy station on the day according to the direct purchase contract electricity between the large user and the new energy station, and calculate the various times of the day of the new energy station according to the required power generation on the day The active power of the active power is divided equally according to the time;

[0049] C. Obtain the power prediction value of the new energy station at each moment of the day, and adjust the active power of the new energy station at each moment according to the power prediction value to obtain the final minimum ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a method for correcting and determining the minimum active power of a new energy station participating in direct electricity purchase of large users. The correcting and determining method comprises the steps that A cross-section data related to participating in direct electricity purchase of large users are acquired; B the required generating capacity on the day of the new energy station is calculated according to the direct electricity purchase contract power of large user and the new energy station, and the active power of the new energy station at each time of the dayis calculated according to the required generating capacity on the day, and equally divided according to time; C the power prediction value of the new energy station at each time of the day is acquired, and the active power of the new energy station at each time is adjusted according to the power prediction value to acquire the final minimum active power of the new energy station; and D steps B and C are repeated until the completion of the generating capacity of the direct electricity purchase contract between large users and the new energy station. The completion rate of new energy stationtrade contracts participating in direct electricity purchase of large users is improved, and at the same time the task of cross-section regulation of a dispatcher is reduced.

Description

technical field [0001] The invention relates to the field of power system scheduling operation and control, in particular to a method for determining the minimum active power correction of new energy stations participating in direct purchase of electricity by large users. Background technique [0002] With the rapid development of new energy technology and the continuous improvement of new energy grid-connected penetration rate, the power grid structure can no longer meet the needs of new energy grid-connected, and some areas rich in new energy have shown that the transmission channel is blocked. When the power generation of a power plant is limited, the dispatching department generally controls it according to the principle that new energy is given priority over traditional energy, and power plants of the same type generate power in equal proportion to installed capacity. [0003] In a market-oriented environment, in order to improve their own competitiveness, some new ener...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): H02J3/00H02J3/48G06Q10/06G06Q50/06
CPCH02J3/008H02J3/48G06Q10/06312G06Q50/06
Inventor 伍仕红姚刚郑凯文陈俊全叶航超安甦张旭黄晓旭安成宋弦肖倩宏
Owner GUIZHOU POWER GRID CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products