Concrete pouring construction method for house building floor same-layer lag synchronous construction
A technology of simultaneous construction and construction method, applied in construction, building structure, formwork/formwork/work frame, etc., can solve the problem of formwork dismantling, etc., so as to reduce workload, save labor, and reduce connection materials and processes. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
[0032] see Figure 1-4 , a concrete pouring construction method of lagging and synchronous construction on the same floor of a house building, comprising:
[0033] (1) Tie the wall reinforcement: tie the N+1th layer wall reinforcement 2 on the formwork supporting platform of the Nth layer wall 1;
[0034] (2) formwork support; after the wall reinforcement is tied, the large formwork system on both sides of the Nth floor wall is hoisted to the N+1 floor and fi...