A construction technology and pipe jacking engineering technology, applied in pipeline laying and maintenance, pipes/pipe joints/fittings, mechanical equipment, etc., can solve the problems of pipeline jacking deviation from the predetermined path, pipeline placement deviation, etc., to improve stability , Improve the effect of using the effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0051] Such as figure 1 As shown, a pipe jacking construction process includes a calibration device 1. The calibration device 1 calibrates the pipeline. Compared with the prior art, the deviation of the pipeline arrangement causes the pipeline to deviate from the predetermined path during the jacking process. , this embodiment achieves the effect of ensuring that the pipeline advances along a predetermined path during the jacking process.
[0052] combine figure 1 and figure 2 , the calibration device 1 includes a base 11, a mounting base 12, a placement box 13 and a plaster block 14, the mounting base 12 is a ring-shaped design whose bottom is fixed to the base 11, and the placement box 13 is detachably fixed to the mounting base 12 The inner wall, and the side of the placement box 13 near the center of the mounting seat 12 is open, the plaster block 14 is placed in the placement box 13 and is detachably fixed with the placement box 13, and the end of the plaster block 14 ...
Embodiment 2
[0056] A pipe jacking engineering construction technique, the construction method comprising the following steps:
[0057] S1. The foundation pit is formed, and a bottom plate is arranged in the foundation pit;
[0058] S2. Measurement and positioning;
[0059] S3. Equipment installation:
[0060] Back installation: form the back wall, and place the back steel plate vertically on the ground in front of the back wall;
[0061] Guide rail installation: Two guide rails are laid in parallel below the pipe jacking path to limit the direction of pipe jacking;
[0062] Hydraulic jack bracket installation: Arrange the driving device on the foundation pit to drive the hydraulic jack bracket; connect the hydraulic jack bracket to the driving device with a high-pressure oil pipe, and place the jack bracket between two guide rails to fix it ;
[0063] Calibration device 1 installation: install the calibration device 1 in front of the pipeline path, place the base 11 of the calibration...