A building wall structure and construction method
A technology for building walls and construction methods, which is applied to building components, building structures, buildings, etc., can solve problems such as low space utilization, troublesome installation, and aesthetic impact, so as to improve space utilization and facilitate the installation of blocks Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0042] Embodiment one: refer to figure 1 , Figure 6 , is a wall structure for building construction disclosed by the present invention, including a concrete wall 1 and a masonry wall, the masonry wall is formed by stacking a plurality of blocks 2, and the concrete wall 1 is formed along the concrete wall 1 The vertical groove 11 is provided in the height direction, and the vertical groove 11 is used to accommodate the block 2, and the length of the vertical groove 11 is the same as the height of the concrete wall 1; figure 2 , image 3 , the block 2 is provided with a through hole 21, the length direction of the through hole 21 is parallel to the thickness direction of the block 2, after stacking a plurality of blocks 2, the axis of the through hole 21 on each block 2 is in the same vertical direction On a straight line, that is, the through holes 21 on a plurality of blocks 2 can form a channel.
[0043] Such as image 3 As shown, the block 2 is provided with a horizont...
Embodiment 2
[0051] Embodiment two: a construction method of a building wall structure, comprising the following steps:
[0052] Step 1: firstly stack the blocks 2 vertically into the vertical groove 11 in turn, so that the stacked blocks 2 form a masonry wall to fill up the vertical groove 11. At this time, the height of the masonry wall is the same as that of the vertical groove 11 The lengths are the same, and the horizontal holes 24 on the block 2 also correspond to the abutting grooves 111 on the inner wall of the vertical groove 11;
[0053] Step 2, insert the connecting rod 3 from the through hole 21 on the top block 2, then insert the rectangular insert rod 71 on the crank handle 7 into the rectangular slot 32, and rotate the connecting rod 3 so that the connecting rod 3 gradually Screw into the reinforcing tube 22 in the through hole 21, let the connecting rod 3 pass through the stacked blocks 2 one after another until it reaches the ground, and let the abutment rod 4 on each bloc...