Mounting method suitable for large area biogas residue pit covering film
An installation method and technology of covering film, which are applied in the direction of excavation, floating bridge, bridge form, etc., can solve the problems of potential safety hazards, time-consuming and laborious, and achieve the effect of avoiding potential safety hazards.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022] For No. 1 biogas residue pit 1 (length 70m, width 50m, area 3500m 2 ) to install the covering film 3:
[0023] (1) Use wooden strips and iron wires to fix two EPS foam boards with a length of 6m and a width of 1.2m;
[0024] (2) According to the area of No. 1 biogas residue pit 1 is 3500m 2 (Length 70m and width 50m), according to the laying principle, the number of foam boards required is calculated to be 176 pieces;
[0025] (3) all the foam boards are connected into pontoon 2, adopt the limit to build pontoon 2 and lay thick 2mm, long 50m, HDPE film with a width of 6m, if first all build pontoon 2 and then lay HDPE film, build a good block Since there is no object pressing on the upper surface of the floating bridge 2, the position will move, so choose to lay the HDPE film while building the floating bridge 2; in addition, before laying the HDPE film, weld several pieces of HDPE film into a whole piece on the open space;
[0026] (4) After the HDPE film is insta...
Embodiment 2
[0028] For the No. 2 biogas residue pit (a circular structure with a radius of 25m and an area of 1962.5m 2 ) to install the covering film:
[0029] (1) Use wooden strips and iron wires to fix two EPS foam boards with a length of 6m and a width of 1.2m;
[0030] (2) According to the area of No. 2 biogas residue pit 1 1962.5m 2 , according to the laying principle, the number of foam boards required is calculated to be 63 pieces;
[0031] (3) all the foam boards are connected into pontoon 2, adopt the limit to build pontoon 2 and lay thick 2mm, long 50m, HDPE film with a width of 6m, if first all build pontoon 2 and then lay HDPE film, build a good block Since there is no object pressing on the upper surface of the floating bridge 2, the position will move, so choose to lay the HDPE film while building the floating bridge 2; in addition, before laying the HDPE film, weld several pieces of HDPE film into a whole piece on the open space;
[0032] (4) After the HDPE film is ...