An optimization method for hydropower cluster operation of leading reservoirs considering market transactions
A technology for operation optimization and hydropower station clusters, applied in water saving, climate change adaptation, data processing applications, etc., it can solve the problems of long-term dynamic process analysis without leading reservoirs, and achieve the effect of strong operability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0151] One provided by the preferred embodiment of the present invention, for example, Table 1 is the hydropower installation schedule in the Yalong River Basin, and Table 2 is the comparison of the power generation capacity of hydropower stations before and after the Yalong River hydropower cluster is put into operation.
[0152]
[0153]
[0154] Table 1
[0155]
[0156] Table 2
[0157] For the Yalong River Basin, an optimization method for the hydropower cluster operation of the leading reservoir considering market transactions, such as figure 1 , mainly including the following steps in sequence:
[0158] S1: Analyze the power generation capacity of the hydropower cluster after the leading reservoir is put into operation, including expected output, guaranteed output and annual power generation indicators;
[0159] In the step S1, after the leading reservoir is put into operation, the power generation capacity of the hydropower cluster mainly includes expected o...