How the stadium was built

A construction method and stadium technology, applied in stadiums, building structures, buildings, etc., can solve the problems of early canopy construction nodes, resource turnover lag, shortening construction period, etc.

Active Publication Date: 2021-12-07
CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The purpose of the present invention is to overcome the defects of the prior art, provide a construction method of the stadium, solve the problem of resource turnover lag and late construction of the canopy, optimize the deployment of resources, save costs, advance the construction node of the canopy, and shorten the construction period. It has high economic benefits and avoids idling and waste of resources as much as possible

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • How the stadium was built
  • How the stadium was built
  • How the stadium was built

Examples

Experimental program
Comparison scheme
Effect test

specific Embodiment approach

[0060] The stadium to be constructed is divided into several layers from bottom to top. Since the volume of the stadium below the evacuation stairs is generally large, the part below the evacuation stairs is taken as the first floor. In addition, the stadium to be constructed is divided along the ring direction. It is an inner zone and an outer zone, and each floor is divided into several unit sections along the radial direction, and several unit sections are joined together to form a ring to facilitate construction;

[0061] The outer area 11 of the first layer and the outer area 21 of the second layer are constructed layer by layer from bottom to top, and then the inner area 12 of the first layer and the outer area 31 of the third layer are constructed simultaneously. The inner zone 12 of the first layer, the outer zone 11 of the first layer, the outer zone 21 of the second layer and the outer zone 31 of the third layer, so the material of the inner zone 22 of the second laye...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method of a stadium, comprising: dividing the stadium to be constructed into several layers sequentially from bottom to top, and dividing the stadium to be constructed into an inner area and an outer area from the inside to the outside along the ring direction; from bottom to top The outer area of ​​N layers and the outer area of ​​N+1 layers are constructed layer by layer, where N is 1, and then the inner area of ​​N layers and the outer area of ​​N+2 layers are constructed simultaneously; the outer area of ​​N layers and N+1 layers The materials are transported to the outer area of ​​the N+3 layer and the inner area of ​​the N+1 layer, and the outer area of ​​the N+3 layer and the inner area of ​​the N+1 layer are constructed simultaneously; the materials of the outer area of ​​the N+2 layer are transported To the inner area of ​​the N+2 layer and the outer area of ​​the N+4 layer, and synchronously construct the inner area of ​​the N+2 side and the outer area of ​​the N+4 layer; then make N=N+1 and execute S14, repeat this Step until construction forms the stadium. The invention effectively solves the problem of lagging resource turnover, optimizes the deployment of resources, saves costs, shortens the construction period, has high economic benefits, and avoids idleness and waste of resources as much as possible.

Description

technical field [0001] The invention relates to the field of building construction, in particular to a method for building a stadium. Background technique [0002] The structure of the stadium is generally trumpet-shaped. The part below the evacuation stairs is larger, while the part above the evacuation stairs is smaller. At present, most stadium construction methods are constructed layer by layer from bottom to top. However, due to the The volume of the lower part is large, and this construction method is likely to cause idle waste of resources. Often after the construction of the first floor is completed, because the concrete requires a long curing time, the materials of the first floor can only be turned over after the construction of the third floor. It is used for the construction of the fourth floor, resulting in a lag in resource turnover, and the canopy needs to wait until the overall construction of the stadium can be installed, which wastes costs and has a long co...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04G21/14E04H3/14
CPCE04G21/14E04H3/14
Inventor 欧亚洲邓程来张德财
Owner CHINA CONSTR EIGHT ENG DIV CORP LTD