Steel box girder self-anchored suspension bridge tower girder synchronous construction method
A technology of tower-beam synchronization and construction method, which is applied in the direction of suspension bridges, bridges, bridge parts, etc., can solve the problems of long construction period of bridges, achieve the effects of speeding up construction progress, shortening construction period, and solving limitations
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The description will be further described below in conjunction with the accompanying drawings and embodiments.
[0032] The method for synchronously constructing tower girders of steel box girder self-anchored suspension bridges implemented according to the present invention includes the following steps.
[0033] Step 1: Refer to figure 1 First set up a steel trestle bridge, construct the bottom foundation of the bridge tower 3, construct the side pier 21, and push the temporary pier 22 of the steel box girder through the steel trestle bridge;
[0034] Step 2: Refer to figure 2 , Figure 6 , on the assembling platform that a plurality of steel box girder pushes away temporary piers 22 to form, assemble framed steel box girder 11, install push away steel guide beam 13, construct bridge tower 3 lower tower columns and tower column pick-up beam 31 simultaneously; Tower column The cantilever beam 31 is located below the main beam 1; the main beam 1 is divided into two l...