Large-area floor flatness control method
A control method and a large-area technology, which is applied in the direction of construction and building construction, can solve problems such as inconvenience, failure to meet leveling requirements, and machine failure to construct, so as to achieve smooth construction progress, realize large-area floor flatness requirements, and save energy. The effect of manpower and construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0021] see now figure 1 , figure 1 It is a schematic diagram of a large-area floor leveling machine paving and track device according to an embodiment of the present invention. The large-area floor flatness control method of the present invention comprises the following steps:
[0022] a. Craft track making
[0023] The main beam is made of 100*60*3 square steel, the auxiliary beam is made of 60*40*3 square steel, and the short column is made of 100*60*3 square steel. part;
[0024] b. Adopt Z-840 laser leveling machine for paving and leveling, so that the concrete laser leveling machine can walk on the craft track for paving and leveling operation;
[0025] c. Use a vibrating ruler to lift the pulp and level it;
[0026] d. N-900 double-disc troweling machine for finishing.
[0027] Among construction machinery and equipment, concrete laser leveling machine paving concrete leveling operation, using vibrating ruler for concrete slurry leveling operation, and double-disc ...