Vibration compaction device and vibration compaction method for backfill area in building construction
A technology of vibratory compaction and building construction, which is applied in the direction of filling, construction, and basic structure engineering, etc., and can solve problems such as uneven distribution of backfill soil and different effects of vibration compaction, so as to achieve improved vibration compaction effect and better return of backfill soil. Tightening, avoiding the effect of collapse
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0047] Such as figure 1 As shown, the vibratory compaction method in the backfill area in building construction includes the following steps:
[0048] Select the backfill soil and lay the backfill soil layer by layer into the foundation pit;
[0049] Every time a layer of backfill is laid, vibratory compaction is carried out once;
[0050] Before vibrating and compacting the backfill, the moisture content of the backfill is monitored in real time;
[0051] Vibrating and compacting the backfill, sucking out the moisture in the backfill through infiltration at a position with a high moisture content of the backfill, and injecting water into the backfill through direct water injection at a position with a low moisture content of the backfill;
[0052] A geogrid is placed under each layer of backfill soil.
[0053] The thickness of each layer of backfill soil is 200-300 mm.
[0054] In the practical application of this embodiment, the backfill soil is screened first, so that t...
Embodiment 2
[0065] Such as Figure 1-7 As shown, on the basis of applying the method of Example 1, this embodiment relates to a vibratory compaction device for a vibratory compaction method in a backfill area during construction, including a front compaction roller 1 and a power vehicle body 2. The compaction roller 1 is provided with a water content balance mechanism 4 , which is fixed with the front compaction roller 1 and extends from the front compaction roller 1 to the outer surface of the front compaction roller 1 .
[0066] In this embodiment, the determination of the water content of the backfill is determined by the conductivity of the backfill, and the measuring electrode 5 needs to be arranged on the front compacting roller 1 in addition to being arranged on the geogrid. The embodiment configures the measuring electrode 5 at the edge position of the front compaction roller 1, and the measuring electrodes 5 are arranged on both sides of the edge, so that the average value of the...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com