Mass concrete pouring system and method
A large-volume concrete, large-volume technology, applied in construction, building structure, construction material processing and other directions, can solve problems such as hidden safety hazards, segregation, and changes in concrete material properties, to solve hidden safety hazards, broad market prospects, and ensure The effect of homogeneity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0041] refer to Figure 1 to Figure 5 , the present embodiment provides a mass concrete pouring method, comprising the steps of:
[0042] Step S1, please refer to figure 1 , figure 2 , dividing a plurality of square pouring radiation areas a on the upper surface of the reinforcement area 5 to be poured with large volume of concrete, and setting a pouring port b on each square pouring radiation area a;
[0043] Step S2, please refer to Figure 5 , lay out the sensor layout layer c within the scope of each square pouring radiation area a, take the square pouring radiation area a as the first layer of the sensor layout layer c, and arrange several sensor layouts at intervals downward in the projection direction of the first sensor layout layer c layer c;
[0044] Step S3, please refer to Figure 4 , setting several concentric square circles d on each sensor layout layer c;
[0045] Step S4, please refer to figure 1 , Figure 4 , Figure 5 , a number of wireless material...
Embodiment 2
[0058] This embodiment provides a large volume concrete pouring system, the technical scheme is as follows:
[0059] refer to figure 1 , a large-volume concrete pouring system, comprising a pouring pipe section automatic lifting device 3, several pouring composite pipes 2, and several wireless material level sensors 1; the pouring composite pipe 2 includes several detachable pipe joints 21 connected in sequence, Pipe 22, pipe joint fixed end 23; the pouring hose 22 is connected to the last detachable pipe joint 21; one end of the pipe joint fixed end 23 is connected to the automatic lifting device 3 of the pouring pipe section, and the other end is connected to the first detachable pipe joint 21 connection; the last detachable pipe joint 21 is provided with a clamping device 4; the clamping device 4 is connected with the automatic lifting device 3 of the pouring pipe section through a steel cable 8; the wireless material level sensor 1 is set in the reinforcement area 5 At di...
PUM