Cast-in-place construction method of cast-in-place concrete bridge
A construction method and technology for bridge construction, applied in bridges, bridge construction, bridge materials, etc., can solve problems such as long construction periods
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0036] The present embodiment provides a kind of cast-in-place construction method of cast-in-place concrete bridge, and it comprises the following steps:
[0037] 1) Measure the bridge construction site, determine the cast-in-place construction plan according to the measurement data, and draw the construction drawings of the supports.
[0038] 2) Then carry out the foundation treatment, erect the full support, install the bottom formwork on the full support in sequence according to the bridge design drawings, and preload and adjust the full support, and then install the web and inner mold on the bottom form, and install the steel skeleton. The preloading and adjustment of the above-mentioned full hall support specifically include the following steps: select sand bags weighed according to the standard weight and load them on the bottom formwork, load the number and position of sand bags according to the bridge design self-weight, and load the sand bags according to the concrete...
Embodiment 2
[0043] The present embodiment provides a kind of cast-in-place construction method of cast-in-place concrete bridge, and it comprises the following steps:
[0044] 1) Measure the bridge construction site, determine the cast-in-place construction plan according to the measurement data, and draw the construction drawings of the supports.
[0045] 2) Then carry out the foundation treatment, erect the full support, install the bottom formwork on the full support in sequence according to the bridge design drawings, and preload and adjust the full support, and then install the web and inner mold on the bottom form, and install the steel skeleton. The preloading and adjustment of the above-mentioned full hall support specifically include the following steps: select sand bags weighed according to the standard weight and load them on the bottom formwork, load the number and position of sand bags according to the bridge design self-weight, and load the sand bags according to the concrete...
Embodiment 3
[0050] The present embodiment provides a kind of cast-in-place construction method of cast-in-place concrete bridge, and it comprises the following steps:
[0051] 1) Measure the bridge construction site, determine the cast-in-place construction plan according to the measurement data, and draw the construction drawings of the supports.
[0052] 2) Then carry out the foundation treatment, erect the full support, install the bottom formwork on the full support in sequence according to the bridge design drawings, and preload and adjust the full support, and then install the web and inner mold on the bottom form, and install the steel skeleton. The preloading and adjustment of the above-mentioned full hall support specifically include the following steps: select sand bags weighed according to the standard weight and load them on the bottom formwork, load the number and position of sand bags according to the bridge design self-weight, and load the sand bags according to the concrete...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com