Closed origin and arrival construction method of shield machine
A construction method and shield machine technology, which is applied in earthwork drilling, shaft lining, tunnel lining, etc., can solve the problems of large soil disturbance, large impact of soil frost heave, long construction period, etc., and achieve the effect of reducing risks
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0032] A construction method for shield machine airtight origination and arrival, the method steps are as follows:
[0033] (1): Make a plain concrete diaphragm wall close to the diaphragm wall enclosure structure;
[0034] (2): Make an oblique observation hole on the door to observe the stability of the soil and the leakage;
[0035] (3): Cut out the concrete and steel bars on the portal in sections, and replace the original continuous wall with plain concrete at the same time;
[0036] (4): Install the receiving device of the shield machine and apply pre-stressing force;
[0037] (5): Fill the steel sleeve of the receiving device to the required height;
[0038] (6): Conduct a pressure test on the steel sleeve;
[0039] (7): The shield machine is excavated until the tail of the shield machine enters or leaves the portal;
[0040] (8): Relieve and disassemble the steel sleeve of the receiving device;
[0041] In order to facilitate a further understanding of the present ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com