Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0077] Let the target BLER of the user's PDCCH be 1%, StepUp is 0.99dB, StepDown is 0.01dB, the initially used CCE aggregation degree CCEinit is 8, the power value previously used by the user is 33.6dBm, and the outer loop factor of the current TTI user is DeltaPDCCH is -2dB, and the remaining PDCCH power Premaind is 60dBm.
[0078] If the user does not receive DCI1 and does not perform ACK / NACK feedback, the base station detects the user's DTX information in the current TTI, so the base station adds an upward adjustment step to the user's outer loop factor, and the current outer loop factor is -1.01 dB.
[0079] The base station determines the CCE aggregation degree set that can be allocated to the user according to the remaining CCE resources CCEremaind in the current TTI, let it be {4}, take a CCE aggregation degree from the CCE aggregation degree set that can be allocated to the user, and take out CCEalloc1, which is 4, The dB value PDCCHres of CCEalloc1 is calculated by ...
Embodiment 2
[0082] Let the target BLER of the user's PDCCH be 1%, StepUp is 0.99dB, StepDown is 0.01dB, the initially used CCE aggregation degree CCEinit is 8, the power value previously used by the user is 33.6dBm, and the outer loop factor of the current TTI user is DeltaPDCCH is -3.02dB, and the remaining PDCCH power Premaind is 30dBm.
[0083] The base station has not detected the user's DTX information in the current TTI, so the base station reduces the user's outer loop factor by a step-down StepDown, and the current outer loop factor is -3.03dB.
[0084] The base station determines the CCE aggregation degree set that can be allocated to the user according to the remaining CCE resources CCEremaind in the current TTI, let it be {2, 4}, and takes a smaller CCE aggregation degree from the CCE aggregation degree set that can be allocated to the user, and takes out CCEalloc1 is 2, and the dB value PDCCHres of CCEalloc1 is calculated by formula (3) to be -6dB. Using formula (4), the user...