A construction technology and technology of embedded parts, applied in the field of leveling construction technology of foundation embedded parts, can solve the problems of embedding elevation displacement, difficult control of axis position and flatness, and easy damage to galvanized layer of embedded parts, etc. Achieve the effect of ensuring flatness and avoiding the elevation error of embedded parts
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0010] The technical solutions of the present invention will be described in further detail below through specific implementation methods.
[0011] A construction technique for leveling foundation embedded parts, which comprises the following steps:
[0012] Step 1: pop up the axis of the foundation embedded part at the base layer, and separate the side line and center line;
[0013] Step 2: Drill holes at the corners of the embedded parts of the foundation, the depth of the drilled holes is 3cm, then implant φ25 steel bars into the holes, and use a ruler to correct the verticality of the steel bars, and set tension bars between the steel bars. Rib, to ensure the rigidity and stability of the steel bar, then weld the nut on the top side of the steel bar, the nut is screwed with a bolt as an adjustment support, and the height of the screw is adjusted so that the height on the top of the nut is 4cm;
[0014] Step 3: Mark the center line of the steel plate as the foundation emb...