Multistage network planned schedule analysis method

An analysis method and technology of hierarchical network, applied in the field of progress analysis of multi-level network planning, can solve problems such as the inability to clearly express activity dependencies, the inability to express the importance of individual activities, and the difficulty in showing the overall picture of large and complex projects.

Active Publication Date: 2013-02-27
北京神舟航天软件技术股份有限公司
View PDF4 Cites 14 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, it has obvious planning and subjectivity, it is difficult to show the whole picture of large and complex projects, it cannot clearly express the d

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Multistage network planned schedule analysis method
  • Multistage network planned schedule analysis method
  • Multistage network planned schedule analysis method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0024] The invention discloses a progress analysis method of a multi-level network plan based on a multi-level network planning model, which is based on the planned start time, planned completion time and planned construction period of each plan, Constraints, calculate the expected start time, expected completion time and planned duration of each plan. Based on this, the user can find the critical path, systematically analyze the longest duration of the project, the probability of completing the project on time and other important indicators, thus, Use network optimization methods to save costs and shorten construction periods. On the basis of this method, through the application of the self-developed computational analysis engine and the integration of third-party graphical display controls, based on the AVPLAN project management platform of Shenzhou Software, the network plan analysis function is realized, and large-scale enterprise-level applications are supported.

[0025]...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a multistage network planned schedule analysis method based on a multistage network planning model, which firstly establishes the multistage network planning model and comprises the following steps: (1) extracting a multistage network plan; (2) arranging a front and rear arrangement relation of the plan; (3) arranging a planning proposal mode; (4) carrying out loop checking to check whether the front and rear arrangement relation of the plan forms a loop or not; (5) executing schedule calculation; and (6) recording the schedule calculation result. According to the invention, on the basis of plan starting time, plan completion time and plan construction period of each plan, the expected starting time, the expected completion time and the plan construction period of the plan are calculated according to the front and rear arrangement relation of the plan and father and son constraint; and on the basis of the expected starting time, the expected completion time and the plan construction period, users can search a critical path, and systematically analyze the longest construction period of the item, the probability of finishing the item on the schedule and other important indices, so as to achieve the purposes of saving cost and shortening the construction period by utilizing a network optimization method.

Description

technical field [0001] The present invention relates to a progress analysis method of a multi-level network plan. Background technique [0002] As we all know, aerospace model engineering is a group management engineering project with very complex cooperation relationship and difficult risk control. With the vigorous development of my country's aerospace industry, the scale of the project has become more and more complex, and there are more and more factors restricting the project, and the pressure to seek benefits through refined management is increasing. Under such circumstances, how to smoothly advance the project progress, make the project well-controlled within the scope of the plan, and ensure that the project achieves its goals "faster and better" is an urgent problem to be solved. At present, in the project management software market, Primavera's P3, P6, Microsoft's Project, etc. are used more. However, in terms of schedule calculation, P3 and P6 do not yet support...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06Q10/06
Inventor 陈凡胡杨博王学敏王泉泉
Owner 北京神舟航天软件技术股份有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products