Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Method for replacing 10kV multi-layered overhead line pole towers with steel pipe poles in situ

A technology for overhead lines and steel pipe poles, which is applied in the field of replacing steel pipe poles for 10kV multi-layer overhead line towers, which can solve problems such as economic loss, aesthetic impact, and easy changes to the status quo of urban streets

Inactive Publication Date: 2013-03-20
JINZHOU ELECTRIC POWER SUPPLY COMPANY OF STATE GRID LIAONING ELECTRIC POWER SUPPLY +1
View PDF3 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The disadvantages of this method are: 1. If the pole tower is replaced in the direction of the horizontal line, the position of the pole tower will be changed, the path of the transmission line will change, which will affect the appearance, and after the path becomes longer, the length of the required wire will be insufficient, and the wire needs to be re-laid , causing economic loss
2. If the pole tower is replaced in the direction of the line, it is easy to change the status quo of the city streets, causing problems such as blocking the entrance of the store, and causing disputes with nearby residents

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for replacing 10kV multi-layered overhead line pole towers with steel pipe poles in situ
  • Method for replacing 10kV multi-layered overhead line pole towers with steel pipe poles in situ
  • Method for replacing 10kV multi-layered overhead line pole towers with steel pipe poles in situ

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0028] Such as figure 1 As shown, the steps of the method for replacing steel pipe poles in situ for the 10kV multi-layer overhead line tower are as follows:

[0029] 1. Erect the cement tower 2 in front of the old tower 1.

[0030] 2. Release the span between the front and rear towers of the old tower 1, so that the transmission line corresponding to the old tower 1 becomes longer. When releasing the span, the release length is the same as the length of the transmission line between the front and rear towers of the old tower 1 The sum is greater than or equal to the line distance between the old tower 1 front tower to the cement tower 2 to the old tower 1 rear tower.

[0031] 3. Move the transmission line on the old tower 1 to the cement tower 2.

[0032] 4. Remove the old pole tower 1, and dig a pole pit at the location of the old pole tower 1.

[0033] 5. Make a steel pipe pole foundation with a flange in the pole pit, and dry it for 7 days until the steel pipe pole foun...

Embodiment 2

[0037] The old tower 1 is an expansion-resistant tower, and there are two cement towers 2, which are respectively located on the left and right sides of the old tower 1, and the others are the same as in the first embodiment.

Embodiment 3

[0039] The old tower 1 is a tower with a single branch, and the cement tower 2 has one. When the branch is biased to the left, the cement tower 2 is located on the left side of the old tower 1. When the branch is biased to the right , the cement tower 2 is located on the right side of the old tower 1.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A method for replacing 10kV multi-layered overhead line pole towers with steel pipe poles in situ includes the following specific steps: cement pole towers are erected nearby an old pole tower; the spans between the old pole tower and the front and the rear pole towers are released; power transmission lines on the old pole tower are transferred onto the cement pole towers; the old pole tower is dismantled, and a pole pit is dug at the position of the old pole tower; a steel pipe pole foundation with a flange is fabricated in the pole pit and dried until the steel pipe pole foundation hardens; a steel pipe pole is connected with and erected by the flange to erect, and the power transmission lines on the cement pole towers are transferred onto the steel pipe pole; the cement pole towers are dismantled, and the pavement is restored even. Since the cement pole towers are erected to serve as media for transferring the power transmission lines, the steel pipe pole can be erected in situ, and moreover, as the steel pipe pole foundation is waited to become hard, power still can be supplied. After completion, the position of the a steel tower is not changed, consequently, the route of the power transmission lines cannot be changed to affect the attractive appearance or the power transmission lines do not need to be re-paid off to cause economic loss, and moreover, the current condition of an urban street cannot be changed to bring about disputes.

Description

technical field [0001] The invention relates to a method for replacing the original steel pipe pole of a 10kV multi-layer overhead line pole tower. Background technique [0002] With the continuous development of economic construction, people's demand for electricity continues to expand, and the requirements for power supply reliability are also constantly increasing. In order to meet people's needs, old towers need to be replaced during power grid transformation. Due to the unbalanced concrete pole towers such as straight branch poles and other pole jacking forces, the guy wires need to be installed in the opposite direction of the pole jacking force, which affects the appearance of the city. Therefore, in the bustling areas of the city, the old cement poles are generally replaced with steel pipe poles that do not need to be installed with guy wires. The method of replacing the steel pipe pole is: excavate the pole pit in the horizontal line direction or along the line di...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04H12/00
Inventor 安雨中刘云松马平田勇甘宇鹏胡浩高东明曹毅新田晋羽王晓亮
Owner JINZHOU ELECTRIC POWER SUPPLY COMPANY OF STATE GRID LIAONING ELECTRIC POWER SUPPLY
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products