A technology for mineral processing plant, water supply and drainage, which is applied in the field of electricity-saving and water-saving complete water supply and drainage units, can solve problems such as the impact on grinding production efficiency and energy efficiency, the impracticality of small and medium-sized mineral processing enterprises, and the high energy consumption of tailings discharge. question
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0025] The structure of this embodiment is as figure 1 As shown, it includes a clean water pump 5, a slurry pump 6 and a thickening tank 13. The top of the thickening tank 13 is connected to a low-concentration tailings pond 14. The discharge end of the clean water pump 5 is connected to the clear water outlet 1 leading to the production area, and the suction end Connect the clean water inlet 2 through the clean water control valve 7 and connect the upper part of the concentration tank 13 through the return water control valve 8; the discharge end of the slurry pump 6 is connected to the tailings outlet 4 leading to the tailings pond, and the suction end is connected to the concentration tank 13 at the bottom; above the thickening tank, there is a tailings inlet 3 connected to the production area, and the connection between the low-concentration tailings tank 14 and the thickening tank 13 is controlled by a low-concentration tailings control valve 16 .
[0026] In this embodim...
Embodiment 2
[0030] This embodiment takes the tailings discharge of a small iron concentrator as an example: the tailings flow rate is 120m 3 / h, concentration 15%, density 1100kg / m 3 , the height difference between the tailings pond and the factory area is 45m, and the loss along the way is 15m. The efficiency of the mortar pump is 40%. The power of the matching mill is 240kW.
[0031] The appearance of this embodiment is as figure 2 As shown, the internal structure is as image 3 As shown, it includes a clean water pump area, a slag slurry pump area and a thickening pool area isolated from each other. The thickening pool area includes a thickening pool 13, and a low-concentration tailings pond 14 is formed by a baffle plate and a clean water pump area above. The baffle plate and the slurry pump area form a tailings buffer pool 15, and the tailings buffer pool 15 is above the tailings inlet 3; the slurry pump area includes a slurry pump 6, and the discharge end of the slurry pump 6 ...