Combined pre-embedded part for concrete wall and column tie bars and its installation and construction method
A concrete wall and construction method technology, applied in the field of building steel bars, can solve the problems of difficult position control, difficult straightening of steel bars, and sliding, etc., and achieve the effects of easy control, improvement of project construction quality and economic benefits, and accurate position
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0049] Such as figure 1 , 2 As shown, a composite pre-embedded part for concrete wall and column tie bars is provided with an iron lath 4, two straight threaded sleeves 3 and two anchor bars 2.
[0050] Iron lath 4 is used for fixing straight thread sleeve 3. Two reserved holes 5 are symmetrically arranged in the middle part of the iron lath 4, and the diameter of the reserved holes 5 is the same as the outer diameter of the straight threaded sleeve 3, and the distance between the two reserved holes 5 is the horizontal distance of two tie bars. Both ends of the iron lath 4 are symmetrically provided with round holes 6 , and the round holes 6 are arranged outside the reserved holes 5 . The diameter of the circular hole 6 is 3mm. The size of iron lath 4 is 200mm * 50mm * 3mm.
[0051] The straight thread sleeve 3 is connected with the column and the wall tie bars. Two straight threaded sleeves 3 are respectively vertically arranged on one side of the iron lath 4 correspondi...
Embodiment 2
[0060] Such as image 3 , 4 , Shown in 5, a composite pre-embedded part for a concrete wall and a column tie bar is provided with an iron lath 4, two straight threaded sleeves 3 and two anchor bars 2.
[0061] Iron lath 4 is used for fixing straight thread sleeve 3. Two reserved holes 5 are symmetrically arranged in the middle part of the iron lath 4, and the diameter of the reserved holes 5 is the same as that of the inner hole of the straight threaded sleeve 3 . The size of iron lath 4 is 200mm * 50mm * 3mm.
[0062] The straight thread sleeve 3 is connected with the column and the wall tie bars. Two straight threaded sleeves 3 are respectively vertically arranged on one side of the iron strip 4 corresponding to the reserved hole 5 . The iron lath 4 and the straight thread sleeve 3 are spot welded, and the weld seam height between the iron lath 4 and the straight thread sleeve 3 is 5mm. A plastic protective plug is provided in the barrel hole at the end of the straight ...
Embodiment 3
[0071] Concrete walls and columns are completed through the production of the pre-embedded parts assembly, positioning of tie bars, installation and fixation of embedded parts, wall formwork support, concrete pouring, form removal, and tie bars inserted into straight threaded sleeves. Installation and construction of tie bars.
[0072] 1. The pre-embedded parts for concrete walls and columns are mainly composed of two straight thread sleeves welded on the iron lath by full welding process. The weld seam is controlled to 5mm. The distance between two straight threaded sleeves is the horizontal distance between two tie bars, and the horizontal distance is not less than one every 100 mm. Vertical spacing setting: arrange 2φ6 tie reinforcement and tie with load-bearing wall or column every 500mm along the wall height. The barrel diameter of the straight thread sleeve is matched with the diameter of the tie bar with the thread to ensure that the tie bar with the thread can penetra...