A technology of diversion tunnels and flood discharge tunnels, applied in construction, water conservancy projects, sea area projects, etc., can solve problems such as difficult to do, large concrete demolition range, small concrete demolition range, etc., to achieve the effect of reducing the heat of hydration
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0023] The method for rebuilding the diversion tunnel body of the present invention into a flood discharge tunnel body comprises the following steps:
[0024] The first step: if figure 1 , 2 As shown, the section of the original diversion tunnel 1 is expanded to the designed expanded section of the flood discharge tunnel;
[0025] The second step: if image 3 , 4 As shown, the vertical reinforcement 2 of the tunnel side wall is installed, and the anchoring agent anchor rod 4 and the pre-embedded steel plate 5 are installed within a certain range at the junction of the precast tunnel side wall 9 and the original diversion tunnel poured side wall 10; The anchor rod 4 extends horizontally outward from the position of the vertical steel bar 2 inside the side wall of the tunnel. The anchor rod 4 is located at the vertical steel bar 2 inside the side wall of the tunnel. Weld to steel bar 2;
[0026] Step 3: If Figure 4 As shown, pour the tunnel side wall 9 and the tunnel roof...