Method for stopping inrushing of goaf water of mine
A technology of old empty water and water blocking, applied in shaft lining, mining equipment, shaft equipment, etc., can solve the problems of frequent occurrence of old empty water in mine water inrush accidents, inability to effectively block old empty water inrush, etc., and achieve cost reduction Low cost, high security and easy implementation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0025] Such as figure 1 , 2 As shown, a method for blocking old empty water inrush in a mine, in a coal mine excavation roadway 2 composed of a main roadway 1, an excavation roadway (a rectangular roadway with a section perimeter of C) 2, and solid coal 3 Inside, a roadway water-blocking section 5 is set 5 meters behind the excavation face 4, and moves forward continuously with the advance of the excavation face. The distance between adjacent water-blocking sections is 5 meters. A flexible water blocking device 6 is arranged in the water blocking section 5 of the roadway.
[0026] The length of the water blocking section 5 of the roadway is three times the perimeter C of the roadway section, and it is arranged along the direction of the roadway. The surrounding water blocking section 5 of the roadway is sprayed with grout 9 so that there are no exposed hard protrusions.
[0027] The flexible water blocking device 6 is composed of a flexible water blocking air bag 61 suspende...
Embodiment 2
[0036] Such as figure 1 , 3 As shown, a method for blocking old empty water inrush in a mine is located in a tunneling work area composed of a main roadway 1, a tunneling roadway (a trapezoidal roadway with a section perimeter of C) 2, and solid coal 3. A roadway water-blocking section 5 is set at a position 5 meters behind the face 4, and it moves forward continuously with the advancement of the excavation face. The distance between adjacent water-blocking sections is 5 meters. A flexible water blocking device 6 is arranged in the section 5 .
[0037] All the other are with embodiment 1.
Embodiment 3
[0039] Such as figure 1 , 4 As shown, a method for blocking old empty water inrush in a mine is located in an excavation work area composed of a main roadway 1, an excavation roadway (a semicircular arch roadway with a section perimeter of C) 2, and solid coal 3. A roadway water blocking section 5 is set at 5 meters behind the excavation working face 4, and it moves forward continuously with the advancement of the excavation working face. The distance between adjacent water blocking sections is 5 meters. A flexible water blocking device 6 is arranged in the water section 5 .
[0040] All the other are with embodiment 1.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com