A hot-rolling rolling schedule planning method

A planning and planning technology, applied in the field of hot steel rolling, can solve the problems of waiting for materials in the production line, increasing the workload of slab warehouse equipment, and unable to prepare rolling plans for slabs.

Active Publication Date: 2017-11-28
SHOUGANG JINGTANG IRON & STEEL CO LTD
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] 1. The implementation of the rolling plan is limited by the strict order of loading materials according to the slab, so it is difficult to adjust the production plan on demand
[0006] 2. Strictly load materials in sequence, increase unnecessary slab inverting operations, increase the workload of slab warehouse equipment, and cause the production line to wait for materials
[0007] 3. If the production conditions cannot be loaded according to the sequence of the rolling sequence, the planner must re-program the rolling sequence to increase the workload of the planner
[0008] 4. It is impossible to compile a rolling plan for the slab that has not yet been produced but will be produced soon, which is not conducive to the production organization of hot delivery and hot loading between steelmaking and hot rolling, and direct loading

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A hot-rolling rolling schedule planning method
  • A hot-rolling rolling schedule planning method
  • A hot-rolling rolling schedule planning method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0052] Such as figure 1 As shown, the present embodiment provides a method for preparing hot rolling roll schedule, including:

[0053] Step S101: The first electronic device creates M virtual slabs according to the information required by the order for the slabs, and the M virtual slabs correspond to M virtual slab numbers respectively, and M is a positive integer, wherein the order is for the slabs Blank requirements information, including: the requirements of the order for the steel type of the slab, the requirements of the order for the specification of the slab, the requirements of the order for the surface of the slab, the requirements of the order for the quantity of the slab Require;

[0054] Step S102: The first electronic device arranges and combines the M virtual slabs according to the hot rolling rules to create a material preparation plan, wherein the material preparation plan includes the M virtual slab numbers;

[0055] Step S103: the first electronic device s...

Embodiment 2

[0082] Based on the same inventive idea, such as image 3 As shown, this embodiment provides a first electronic device, including:

[0083] The first creating unit 201 is used to create M virtual slabs according to the information required by the order for the slabs, the M virtual slabs correspond to M virtual slab numbers respectively, and M is a positive integer, wherein the order Requirements for slabs, including: the order’s requirements for the steel type of the slab, the order’s requirements for the slab’s specifications, the order’s requirements for the surface of the slab, the order’s requirements for the slab Quantity requirements;

[0084] The second creation unit 202 is configured to arrange and combine the M virtual slabs according to hot rolling rules to create a material preparation plan, wherein the material preparation plan includes the M virtual slab numbers;

[0085] A sending unit 203, configured to send the material preparation plan to the second electron...

Embodiment 3

[0088] Based on the same inventive idea, such as Figure 4 As shown, this embodiment provides a second electronic device, including:

[0089] A receiving unit 301, configured to receive a material preparation plan sent by the first electronic device;

[0090] The first output unit 302 is configured to output first notification information, the first notification information is used to notify the slab warehouse to prepare materials according to the material preparation plan, so that the slab warehouse can obtain the M virtual slabs Corresponding M real slabs.

[0091] Optionally, in this embodiment, the second electronic device further includes:

[0092] The second output unit 303 is used to notify the slab warehouse to prepare materials according to the material preparation plan, and output second notification information after obtaining M real slabs corresponding to the M virtual slabs, the second notification information It is used to notify the slab warehouse to load the...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a hot rolling roll period planning method. The method comprises the steps that first electronic equipment establishes M virtual slabs according to information of the requirements for slabs of an order, wherein the M virtual slabs correspond to M virtual slab numbers respectively, M is a positive integer, and the information of the requirements for the slabs of the order comprises the requirement for the slab steel grade of the order, the requirement for slab specifications of the order, the requirement for slab surfaces of the order and the requirement for slab quantity of the order; the first electronic equipment performs permutation and combination on the M virtual slabs according to hot rolling rules and establishes a material preparation plan, wherein the material preparation plan contains the M virtual slab numbers; the first electronic equipment transmits the material preparation plan to second electronic equipment.

Description

technical field [0001] The invention relates to the technical field of hot rolling of iron and steel, in particular to a method for preparing a roll schedule plan for hot rolling. Background technique [0002] The hot rolling production operation planning and scheduling in the iron and steel industry is the link between the production organization of the steelmaking plant and the hot rolling plant. [0003] Since the preparation of hot rolling production plan requires strict combination of rolling material thickness and width jump rules to form a "coffin-shaped" sequence, and taking into account the user's surface quality requirements, hot hardness of the product during rolling, and wear of the roll, etc., the production operation plan (rolling system), while the slab stacking in the slab warehouse is multi-layer stacking (generally 12 or 14 layers). In the process of executing the production operation plan in the slab warehouse, the slab loading must be lifted from top to ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): G05B19/418G06Q10/06
CPCY02P90/02
Inventor 刘武华林绍峰刘文广刘木刚郭亮王帅卢杰王东宋海洋李鹏
Owner SHOUGANG JINGTANG IRON & STEEL CO LTD