[0027] The present invention will be further described in detail below through the specific examples, the following examples are only descriptive, not restrictive, and cannot limit the protection scope of the present invention with this.
[0028] A kind of construction method of the water-stop curtain that changes soil and stirs, and the steps of its method are:
[0029] ⑴. The pilot hole pile position is placed according to the axis of the cement mixing pile; the pilot hole pile position is placed according to the axis of the three-axis mixing pile φ1000@1200.
[0030] (2) Embed the steel casing and use mud to stabilize the hole wall. The mud is made of high-quality clay mixed with water and mixed with a certain proportion of bentonite to prepare the mud. The wet operation of the rotary excavator removes the soil to be excavated in the hole; the height of the steel casing is 2m, the diameter of the steel casing is 20cm larger than the designed pile diameter, and the top surfa...