Soil changing mixing waterproof curtain construction method based on pebbles
A technology of water-stop curtain and construction method, which is applied in basic structure engineering, construction, sheet pile wall and other directions, can solve the problems of incompatibility, high process cost and high cost of ground connecting wall, and achieves good water-stop effect, simple process, low cost effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] The present invention will be further described in detail below through the specific examples, the following examples are only descriptive, not restrictive, and cannot limit the protection scope of the present invention with this.
[0029] A pebble-based soil replacement and stirring water-stop curtain construction method, the steps of the method are:
[0030] ⑴, according to the axis of the cement mixing pile, the pilot hole pile position is placed; the pilot hole pile position is placed according to the axis of the three-axis mixing pile, and the pilot hole pile position is φ10001200.
[0031] (2) Embed the steel casing and use mud to stabilize the hole wall. The mud is made of high-quality clay mixed with water and mixed with a certain proportion of bentonite to prepare the mud. The wet operation of the rotary excavator removes the soil to be excavated in the hole; the height of the steel casing is 2m, the diameter of the steel casing is 20cm larger than the designed...