A technology of transverse prestressing and reinforced concrete, which is applied in the direction of erecting/assembling bridges, bridges, bridge parts, etc., which can solve problems such as weak transverse connections, insufficient bridge bearing capacity, and poor transverse distributed load capacity, and achieve simple materials and construction tools , increase the safety factor of the bridge, and the effect of high technical maturity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0039] Example: (see figure 1 )
[0040] A prestressed concrete hollow slab bridge with a bridge width of 10m (the width of the bridge deck is 9m + the width of the anti-collision belt 10 is 2×0.5m), the longitudinal level is horizontal, and the transverse slope is 1.5%. Length × width × thickness = 1996cm × 99cm × 85cm, the load is road— Level, hinge joint concrete and bridge deck pavement concrete 4 and anti-collision strip 10 concrete are C40 respectively;
[0041] The original bridge deck pavement concrete 4 is cut at the bridge deck joint, the hinge joint concrete and the original bridge deck pavement concrete 4 have been chiseled off, and the connection between the bridge decks has been disconnected;
[0042] It is required to use the original bridge slab, and apply transverse prestress to the bridge deck pavement for reconstruction; the center spacing of the steel mesh reinforcement is 10cm, and the center spacing of the horizontal steel strands 1 is not greater than...