Construction method for digging pile with pile top elevation below natural ground

A construction method and hole-digging pile technology, which are applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of long time for earthwork excavation, secondary road construction on site, and inability to accurately embed steel column embedded parts. , to avoid road maintenance, save construction period, prevent installation from being in place or unable to install

Active Publication Date: 2016-11-09
CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF7 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, when the pile top elevation is below the natural ground, especially when it is 2 meters or less below the natural ground, it is impossible to accurately embed the steel column embedded parts directly on the natural ground.
[0004] At present, when the elevation of the pile top of the artificially excavated pile is 2 meters below the natural ground, the soil layer is first excavated to the elevation of the cap cap, and then the manual excavation pile is carried out. The construction is convenient and the positioning is simple. The disadvantages are: the earth excavation takes a long time, and the site needs secondary road repairs.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for digging pile with pile top elevation below natural ground
  • Construction method for digging pile with pile top elevation below natural ground
  • Construction method for digging pile with pile top elevation below natural ground

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0033] The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.

[0034] see first figure 1 Shown, the excavation pile construction method of the present invention's pile top elevation below the natural ground mainly comprises following construction technology:

[0035] S001: Excavate holes for excavated piles on natural ground;

[0036] S002: Install pile reinforcement cages in the pile holes of excavated piles;

[0037] S003: Position and install the pre-embedded column foot in the pile hole of the excavated pile;

[0038] S004: Pouring pile concrete in the pile hole of the excavated pile to the pile top elevation;

[0039] S005: Excavate the earth above the pile top level of the excavated piles.

[0040] Hole-digging piles refer to the piles in which the pile holes are formed by manual excavation, then the pile reinforcement cage is placed, and the pile concrete is poured. Hole-digging piles...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method for a digging pile with the pile top elevation below the natural ground. The method comprises the steps that a digging pile hole is dug in the natural ground; a pile reinforcement cage is mounted in the dug digging pile hole; an embedment column leg is mounted in the digging pile hole in a positioned mode; pile concrete is poured into the digging pile hole till the pile top elevation; and earth above the pile top elevation of the digging pile is dug. Through the modes that construction of the digging pile is conducted at first instead of excavating the earth, and a construction person performs positioning mounting of the embedment column leg in the pile top before pouring of the pile concrete, on the one hand, the project period can be shortened, road maintenance is avoided, and cost is reduced; on the other hand, the mounting precision of the embedment column leg can be accurately mastered, and the embedment column leg is prevented from shifting in the pouring vibration process of the pile concrete, so that accurate positioning of a supporting steel column of an upper main building structure mounted based on the embedment column leg is ensured.

Description

technical field [0001] The invention relates to the field of building construction, in particular to a method for constructing hole-digging piles whose pile top elevation is below the natural ground. Background technique [0002] Manual digging pile refers to the pile that is made by manual excavation, and then the steel cage is placed, and the concrete is poured. Manual hole-digging piles are generally thicker in diameter, and the thinnest is more than 800 mm. They can bear structural bodies with fewer floors and higher pressure, and are currently widely used. Set caps on the top of the piles, and then use the caps to tie and connect them. The top of the piles is equipped with steel column embedded parts, which are used to locate and install the load-bearing steel columns of the superstructure, so that the force of each pile is evenly distributed. , to support the entire building. Therefore, the installation accuracy of the steel column embedded parts directly affects the...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D5/36
CPCE02D5/36
Inventor 符洪刚郭小涛马旭江董金龙苟德鹏童海波
Owner CHINA CONSTR EIGHT ENG DIV CORP LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products