Building Level Measurement Method
A level measurement and construction technology, applied in height/level measurement, measuring devices, surveying and navigation, etc., can solve the problems of undiscovered errors, surveyors do not know the height of the instrument, and cannot directly read the error value of the template, etc. achieve the effect of avoiding mistakes
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] Such as figure 1 Shown, adopt method of the present invention to carry out the construction survey of benchmarking point to building, comprise the following steps:
[0029] Step (1): Select lead survey point 2, determine the survey height of the benchmark point and the position of the survey point, and determine the position of the survey point according to the positions of lead survey point 2 and the survey point.
[0030] Step (2): set up a level 1 at the station, place a scale at the lead point 2, and determine the height to be measured of the scale, the height to be measured is the height of the benchmark minus the height of the lead point difference; figure 1 As shown, if the height of the lead measurement point 2 is ±0.00m, the measurement elevation of the benchmarking point is set to +1.00m, and the said measurement height should be +1.00m.
[0031] Step (3): Adjust the height of the level 1 to the position where the height should be measured on the scale align...
Embodiment 2
[0045] In the construction of the floor formwork platform, it is necessary to check the error value of the beam and platform formwork. If it exceeds the requirements of the specification, it must be adjusted to the allowable range of the specification before the construction of the subsequent process. Assuming that the elevation of the lead measuring point is ±0.00m, assuming that the thickness of the concrete to be constructed by the platform is 0.12m, the measurement method of the present invention is used to measure, including the following steps:
[0046] (1). Select the leading measurement point, the elevation of the leading measurement point is ±0.00m, determine the elevation of the floor level point to be +1.4m (the elevation of the upper surface of the floor template after the floor is constructed should be +0.00m), and determine the measurement point s position, figure 2 The middle rectangular box represents the floor formwork platform, and the dots in the rectangula...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 