A technology for operating platforms and construction methods, which is applied in the direction of construction, building structure, scaffolding supported by house structures, etc., can solve problems such as inconvenient construction, hidden safety hazards, and influence of shaft walls, so as to facilitate demolition and reduce construction costs , Improve the effect of stability and security
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] see Figure 1 to Figure 3 , the present embodiment provides a tool-based operating platform for masonry shaft walls 1, including: at least two channel steel brackets 2 arranged along the short-span direction at the shaft opening and laid on the channel steel brackets 2 Scaffold board 3, one end of the channel steel bracket 2 is detachably fixedly connected to the core tube wall 6, and the other end of the channel steel bracket 2 is detachably fixedly connected to the guide wall 7, and each channel steel bracket 2 is provided with a pressure bar for pressing the scaffold board 3 on the channel steel bracket 2, one end of the pressure bar 4 is movably connected with one end of the channel steel bracket 2, and the pressure bar 4 can Rotate around the active connection point between the pressure bar 4 and the channel steel support 2. The quantity of described depression rod 4 is identical with the quantity of described channel steel support 2, and the length of described d...
Embodiment 2
[0038] see Figure 1 to Figure 3 , the present embodiment provides a construction method for the shaft wall 1, using the tool-based operation platform for building the shaft wall 1 as described in the first embodiment, the method includes:
[0039] Step 1: Install at least two channel steel brackets 2 along the short-span direction at the shaft opening, one end of the channel steel bracket 2 is detachably fixed on the core tube wall 6, and the other end of the channel steel bracket 2 is detachable fixed on the guide wall 7, each channel steel bracket 2 is provided with a pressure rod 4, one end of the pressure rod 4 is movably connected with one end of the channel steel bracket 2, and the pressure rod can be wound around the pressure rod 4 The active connection point between the channel steel bracket 2 rotates. In order to improve the stability and safety of the operating platform, the distance between the channel steel bracket 2 is less than or equal to 1800mm, and the distan...