Accuracy control method for bolted-type web member hole group of steel pipe arch
A technology of precision control and steel pipe arch, which is applied in the erection/assembly of bridges, bridges, buildings, etc., which can solve the problems of high cost and low precision, and achieve the effects of reducing construction difficulty, improving production efficiency, and ensuring accuracy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0026] The method for controlling the accuracy of steel pipe arch bolted web hole group comprises the following steps:
[0027] see figure 1 , provide gusset plate 1, after gusset plate 1 blanking is completed and checked, use CNC drilling machine or radial drilling machine to drill hole groups according to the construction drawing of gusset plate 1, and draw the gusset plate based on the drilled hole group Install positioning line 2;
[0028] see figure 2 , according to the coordinates of the tire map, set out the installation positioning line 3 of the arch rib gusset plate, and make the arch rib pipe joint to lengthen the tire;
[0029] After the arch-rib pipe joint is connected to the ground tire, return the arch rib gusset plate installation positioning line 3 on the pipe joint according to the ground tire positioning point;
[0030] Please ref...