A construction method and composite foundation technology, which is applied in infrastructure engineering, drilling equipment and methods, earthwork drilling and mining, etc., can solve problems such as inability to fill in compaction, and achieve the effects of convenient construction, reduced voids, and strong bearing capacity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0069] Such as Figure 5 As shown, the construction method of a column-hammer rammed and expanded pile composite foundation provided in this embodiment includes:
[0070] Step S101, disassembling the column head 2 from the hammer body 1;
[0071] Step S102, placing the grouting pipe 3 in the hole;
[0072] Step S104, adding filler into the hole and tamping the filler in the hole through the hammer body 1 .
[0073] The specific operation process is as follows:
[0074] In step S101 of disassembling the column head 2 from the hammer body 1 , fix the hammer body 1 , and use a torque wrench or other auxiliary equipment to disassemble the column head 2 from the hammer body 1 . Subsequently, step S102 is performed to place the grouting pipe 3 in the hole, and the upper end of the grouting pipe 3 should leak 1-2m above the ground. In step S104, adding filler to the hole and tamping the filler in the hole through the hammer body 1, you can first add part of the filler into the ho...
Embodiment 2
[0076] Such as Figure 6 As shown, the construction method of a column-hammer rammed and expanded pile composite foundation provided in this embodiment includes:
[0077] Step S101, disassembling the column head 2 from the hammer body 1;
[0078] Step S1021, passing the grouting pipe 3 through the through hole 11;
[0079] Step S1022, placing the hammer body 1 and the grouting pipe 3 together in the hole;
[0080] Step S103, taking out the hammer body 1 in the hole;
[0081] Step S104, adding filler into the hole and tamping the filler in the hole through the hammer body 1;
[0082] Step S105, inject grout into the hole through the grouting pipe.
[0083] The specific operation process is as follows:
[0084]In step S101 of disassembling the column head 2 from the hammer body 1 , fix the hammer body 1 , and use a torque wrench or other auxiliary equipment to disassemble the column head 2 from the hammer body 1 . In step S1021 , the grouting pipe 3 is passed through the t...