Method for temporary segmentation of distribution network
A temporary, ring network technology, applied in the installation of cables, AC network circuits, cable installation devices, etc., can solve the problems of complex construction vehicles, equipment and personnel, long operation duration, and high meteorological conditions, so as to avoid equipment reliability. The effect of reducing the reliability of power supply and power supply, minimizing the construction scope of power outages, and reducing the number of outage users
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] Such as figure 1 As shown, the method for the temporary segmentation of the distribution network of the radial connection mode proposed by the present invention specifically includes the following steps:
[0031] S1. Carry out on-site scheme investigation for the construction section of planned maintenance, determine the wiring mode of the planned maintenance section and optimize the pre-installed bypass switch and flexible cable tower;
[0032]S2. When the planned maintenance line is radial wiring, select the tower next to the first planned maintenance section 8 as the bypass switch and install point A 5;
[0033] Before the start of the planned maintenance project, if the meteorological conditions permit, use the diversion line to install the bypass switch to install the tower at point A. Install the first bypass switch 6 with live load on point A 5, use the first flexible cable 7 with a quick plug-in interface as the connecting lead, connect the bypass switch to ins...
Embodiment 2
[0037] Such as figure 2 As shown, the method for the temporary segmentation of the distribution network of the ring network connection mode proposed by the present invention specifically includes the following steps:
[0038] S1. Carry out on-site scheme investigation for the construction section of the planned maintenance, determine the wiring mode of the planned maintenance section and optimize the pre-installed bypass switch and flexible cable tower;
[0039] S2. When the planned maintenance line is the ring network connection mode,
[0040] Before the maintenance, determine the power supply on the opposite side of the planned maintenance line 14, and realize that the two ends of the second planned maintenance section 16 are respectively connected to the corresponding power supply I9 and power supply II23. The pole tower at point B and the bypass switch are installed at point C. The pole tower at point C is changed from a straight pole to a tension pole type under the sta...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com