A field progress monitoring system and a method based on a three-dimensional model

A 3D model and monitoring system technology, applied in the direction of instruments, data processing applications, resources, etc., can solve problems such as untimely update of progress, impact of construction progress evolution, poor ability to adjust construction progress plans, etc., and achieve the effect of facilitating real-time monitoring

Inactive Publication Date: 2019-02-22
GUANGXI ROAD & BRIDGE ENG GRP CO LTD
View PDF7 Cites 45 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

There are often various factors that affect the construction progress during the construction process. The traditional construction site progress monitoring methods often have problems such as untimely progress updates and poor ability to adjust construction progress plans.
During the construction process, the realization of the evolution of the construction schedule is often affected by various reasons, such as planning defects, changes in the construction environment, adjustments to site conditions, impacts on resource supply, etc. The construction plan needs to be adjusted in time, but due to the progress The update is not timely, and the construction schedule based on the construction network diagram cannot directly reflect the key factors that cause the deviation of the construction schedule, so it is impossible to prepare a targeted project schedule in time

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A field progress monitoring system and a method based on a three-dimensional model

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] The present invention will be further described below in conjunction with the accompanying drawings and embodiments. It should be noted that the specific embodiments of the present invention are only for the purpose of describing the technical solution more clearly, but not as a limitation of the protection scope of the present invention.

[0027] A three-dimensional model-based on-site progress monitoring system, including a BIM model device, a schedule preparation module, a construction progress simulation module, a monitoring management platform and an external intelligent mobile device; the BIM model device is connected to the progress preparation module, and the progress Both the compilation module and the external intelligent mobile device are connected to the monitoring and management platform;

[0028] The BIM model device is used to obtain model design data, generate a BIM model, and store the BIM model in the server;

[0029] The schedule compilation module i...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention belongs to the technical field of project schedule management. The invention relates to a field progress monitoring system based on three-dimensional model, comprising a BIM model device, a progress compiling module, a construction progress simulation module, a monitoring management platform and an external intelligent mobile device. The BIM model device is used for generating a BIMmodel; the progress compiling module is used to obtain the relevant data of the components in the BIM model and compile the construction schedule. The construction progress simulation module is used to correlate the construction progress plan with the BIM model to simulate the construction progress. The external intelligent mobile device is used for inputting the actual construction progress of the site to the monitoring management platform according to the project content; the monitoring management platform is used to compare the actual progress with the construction progress plan to obtain the project progress information, which is displayed in the BIM model in a colored manner. The invention effectively combines the BIM with the construction progress plan, realizes the intercommunication and sharing of the information, and improves the efficiency and the precision of the project progress monitoring and management.

Description

technical field [0001] The invention belongs to the technical field of engineering project progress management, and in particular relates to a three-dimensional model-based on-site progress monitoring system and method. Background technique [0002] Project progress monitoring occupies a very important position in the three major controls of project management—investment control, progress control and quality control. There are often various factors that affect the construction progress during the construction process. The traditional construction site progress monitoring methods often have problems such as untimely progress updates and poor ability to adjust construction progress plans. During the construction process, the realization of the evolution of the construction schedule is often affected by various reasons, such as planning defects, changes in the construction environment, adjustments to site conditions, impacts on resource supply, etc. The construction plan needs ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/06G06Q10/10G06Q50/08
CPCG06Q10/06312G06Q10/103G06Q50/08
Inventor 王伟宁王建军林广泰孙辉罗伟陆进陆艺杨威杨文达陈旺平陈孝强李雍友
Owner GUANGXI ROAD & BRIDGE ENG GRP CO LTD
Features
  • R&D
  • Intellectual Property
  • Life Sciences
  • Materials
  • Tech Scout
Why Patsnap Eureka
  • Unparalleled Data Quality
  • Higher Quality Content
  • 60% Fewer Hallucinations
Social media
Patsnap Eureka Blog
Learn More