A technology of construction technology and main tower, applied in construction, bridge construction, bridges, etc., can solve the problems of low construction work efficiency, consumption of materials and labor, narrow operation space, etc., to achieve the effect of ample operation space and improvement of construction efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0033] A kind of main tower column construction technology among the present invention, comprises the following steps: Main tower column is divided into two construction sections from bottom to top, and described construction section comprises the first construction section at the bottom and the first construction section at the first construction section. The second construction section above;
[0034] The first construction section carries out tower column construction by erecting supports;
[0035] The second construction section carries out the tower column construction by erecting a stiff framework, and the stiff framework forms the overall steel structure of the second construction section of the tower column, and the surrounding sides of the stiff framework are composed of several interconnected steel bars Composition, the inner side of the rigid skeleton is provided with an installation space for steel strands;
[0036] Hydraulic climbing formwork and formwork reinfor...
Embodiment 2
[0053] In this embodiment, it is necessary to mechanically construct the main tower column of the Zhaohua Bridge. The main tower column of the Zhaohua Bridge adopts a large curved lotus shape with an outer curve radius of 325m and an inner curve radius of 270m and 300m, with a height of 100.8m. 23 construction sections, the standard section height is 4.5m, the concrete grade is C55, and it is a large-volume concrete project. The construction time spans winter, and the concrete crack control construction is difficult; Different curve designs greatly increase the difficulty of climbing formwork construction; vertical prestressed steel strands are installed inside the tower column, with a maximum length of 52.54m and a heaviest weight of about 6t.
[0054] The first phase of the G320 Xiangtan Ring Road Project is located in Xiangtan City, Hunan Province. It is a key project in Hunan Province. It has a total length of 5.1km and is divided into three contract sections. The first and...