Method using flange device for structural reserved hole construction
A technology of reserved opening and construction method, applied in the field of flange device and structural reserved opening construction, can solve the problems of long construction period, large wind influence factors, high fixing difficulty and high cost, and achieve good waterproof effect, low cost, Simple construction effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] Below in conjunction with accompanying drawing and embodiment the present invention will be further described:
[0021] Such as figure 1 , figure 2 as well as image 3 As shown, a flange device disclosed in the present invention is used in the construction method of the reserved opening of the structure, which specifically includes the following construction steps. In this case, a floor slab with a thickness of 120mm is used as an example to illustrate:
[0022] S1: After the steel structure has completed the installation of the profiled steel plate 7 and the binding of the floor steel bars 8, conduct on-site measurement and setting out of the reserved openings on the floor plane to obtain the plane positions of all reserved openings;
[0023] S2: Select the specification of the flange device according to the thickness of the floor structure;
[0024] The structure of the flange in this case is as follows figure 2 As shown: the flange device includes a flange tube...