Combined complete grounding equipment and grounding construction method
A kind of grounding equipment and combined technology, applied in the direction of connecting contact materials, etc., can solve the problems that the position of the iron tower is not fixed, cannot meet the complex and changeable grounding construction requirements, and the soil resistivity is different, and achieve the effect of meeting the grounding requirements
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] As shown in the figure: a combined grounding equipment set, with:
[0044] Armored graphite down conductor, armored graphite down conductor is composed of connecting terminal and graphite down conductor, graphite down conductor includes stainless steel core plate, flexible graphite braid wrapped outside the stainless steel core plate and wrapped Stainless steel braided protective layer outside the flexible graphite braiding layer, one end of the graphite down-conductor is crimped with the connection end, the other end of the graphite down-conductor is the graphite grounding strap connection end, and the graphite down-conductor is sleeved with insulation layer.
[0045] Armored graphite down conductors include cable armored graphite down conductors and ribbon armored graphite down conductors. The diameter of cable armored graphite down conductors is 20mm or 28mm, and ribbon armored graphite The size of the down conductor is 40cm*5cm or 60cm*8cm. The stainless steel cor...
Embodiment 2
[0054] A method for grounding construction using a combined set of grounding equipment: measuring the resistivity of the soil around a subway tower to be grounded;
[0055] If the resistivity of the soil is less than or equal to 1000Ω·m, dig square ditches around the four tower legs of the iron tower, then connect the connecting end of the armored graphite down conductor to the tower legs of the iron tower, and use a clamp to connect the graphite grounding strip Connect with the other end of the armored down conductor, spread a layer of graphite cloth or graphite blanket on the bottom of the ditch, and then spread the graphite grounding belt on the graphite cloth or graphite blanket, and fill the ditch.
[0056] The soil resistivity of most terrains is about 100Ω•m. After construction around the iron tower, it is required to reduce the grounding resistance to less than 15Ω. For a transformer with a capacity of 100KW, it is required to reduce the grounding resistance to below 4Ω...
Embodiment 3
[0064] A method for grounding construction using a combined set of grounding equipment: measuring the resistivity of the soil around a subway tower to be grounded;
[0065] If the resistivity of the soil is greater than 1000Ω·m, dig a square trench along the four tower legs of the iron tower, then connect the connecting end of the armored graphite down conductor to the tower legs of the iron tower, and use a clamp to connect the graphite grounding strip Connect with the other end of the armored down-conductor, lay a layer of graphite cloth or graphite blanket on the bottom of the ditch, and then dig radiation ditches at the four corners or the middle points of the four sides of the square ditch. Lay the graphite belt and graphite cloth, and connect the graphite grounding module or the quick-installed ion grounding electrode through the clamp on the graphite belt.
[0066] The above method can also be referred to as "enclosed frame + ray + graphite grounding module + quick-inst...
PUM
| Property | Measurement | Unit |
|---|---|---|
| diameter | aaaaa | aaaaa |
| size | aaaaa | aaaaa |
| electrical resistivity | aaaaa | aaaaa |