A method for realizing rapid start of denitrification in low temperature period of deep bed filter
A rapid start-up and denitrification technology, applied in chemical instruments and methods, anaerobic digestion treatment, water treatment under temperature conditions, etc., can solve the problems of long start-up time in low temperature period, and achieve simple operation process, shorten start-up time, and key parameters clear effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment approach 1
[0025] When the water temperature drops to 20 °C, the deep bed filter starts the carbon source dosing system, and the carbon source is initially added according to the externally added COD concentration of 20-30 mg / L. After the operation is stable, the COD and nitrate nitrogen in the filter inlet and outlet water According to the test results, the concentration of the carbon source is adjusted accurately, and the COD of the external carbon source is controlled to not be lower than 20mg / L. After 7 to 10 days, the denitrification is completed and the initial denitrification filming of the first stage is started in advance;
[0026] Starting from the end date of the first stage, the denitrification function is maintained in the second stage. When the filter only needs to perform the filtering function for more than 20-25d of the set carbon source start-up period, 20-25d is used as a start-up period. Add carbon source to the filter, the concentration of COD of carbon source is 5-10...
Embodiment approach 2
[0029] When the water temperature drops to 20 °C, the deep bed filter starts the carbon source dosing system, and the carbon source is initially added according to the externally added COD concentration of 20-30 mg / L. After the operation is stable, the COD and nitrate nitrogen in the filter inlet and outlet water According to the test results, the concentration of the carbon source is adjusted accurately, and the COD of the external carbon source is controlled to not be lower than 20mg / L. After 7 to 10 days, the denitrification is completed and the initial denitrification filming of the first stage is started in advance;
[0030] Starting from the end date of the first stage, enter the second stage of denitrification function maintenance, the filter only needs to perform the filtering function for less than 20 to 25 days after the set carbon source start-up period, end the second stage and enter directly into denitrification. Recovery starts the third stage.
[0031] When ente...
experiment example
[0033] The present invention and the traditional deep bed filter denitrification start-up method were compared in parallel, and a simulation device of a deep bed filter of a city sewage treatment plant in the north was established. The filter influent is the sedimentation tank effluent. Table 1, the operating parameters of the present invention and the traditional deep bed filter denitrification start-up method are shown in Table 2.
[0034] Table 1 Influent water quality of deep bed filter
[0035] project COD(mg / L) NO 3 - -N(mg / L)
The first stage 10.9-14.5 7.8-9.5 second stage 9.9-22.7 8.5-9.4 The third phase 9.1-16.1 10-14.2
[0036] Table 2 Operational parameters of the present invention and traditional deep bed filter denitrification start-up method
[0037]
[0038] Effluent NO from the filter 3 - -N is 9.5mg / L as the set target. The stable time and effect of denitrification in the low temperature period of the two start...