[0034] The present invention will be described in further detail below in conjunction with the accompanying drawings and embodiments.
[0035] The embodiment of the present invention provides a layered construction method suitable for the height of the bridge tower and the beam on the haunch, which includes the following steps:
[0036] S1: see figure 1 As shown, between the poured sections 10 of the two tower columns 1, a construction support 2 is installed at the design position;
[0037] Specifically, the embedded part 14 is installed at the design position, and the prestressed beam in the circumferential prestressed pipe in the tower column 1 near the embedded part 14 is tensioned and grouted; and then the embedded part 14 is welded A corbel 15, a spacer is installed on the corbel, and a support bottom distribution beam 16 is installed on the spacer;
[0038] see figure 2 As shown, the construction support 2 is assembled by a plurality of support units 20 of the same s...