Concrete transport vehicle scheduling method and device, terminal equipment and readable storage medium
A technology for a concrete transport vehicle and a scheduling method, which is applied in the field of vehicle management and can solve the problems of error-prone manual scheduling and scheduling.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0050] In this example, see figure 1 It is shown that a concrete transport vehicle scheduling method includes the following steps:
[0051] S10: Get the production plan.
[0052] Terminal equipment for dispatching concrete transport vehicles can receive production planned production plans transmitted by the production plan, managing dispatched concrete transport vehicles, can also manually enter production planning orders through terminal equipment, and dispatching concrete can also dispatch concrete The terminal device of the transport vehicle is connected to the storage device stored in the production plan, and the production plan in the storage device is imported into the terminal device.
[0053] S20: Determine the predetermined number of target mixing plants, target tasks, and concrete transport vehicles, based on the production plan.
[0054] Terminal equipment for dispatching concrete transport vehicles analyzes the acquired production plan, determines the target mixing st...
Embodiment 2
[0061] In this example, see figure 2 It is determined that the method of the predetermined number of target concrete transport vehicles includes the following steps:
[0062] S31: The concrete transporter that will wait scheduling is nestled from near to the target stirring station.
[0063] S32: The concrete transport vehicle that is the same distance from the target stirring site is sorted from the respective dispatched single priority coefficients.
[0064] S33: Select the predetermined number of concrete transport vehicles before the sort result as the target concrete transport vehicle.
[0065] Demonstrative, waiting scheduled concrete transport vehicles have 5, the distance between the 1st concrete transporter is 500m, the sender's priority coefficient is 85; the distance between the 2nd concrete transport vehicle distance target mixing station is 550m. The sender's priority coefficient is 95; the distance between the 3-vehicle transporter distance is 540m, the sender prior...
Embodiment 3
[0069] In this example, see image 3 It is shown that a concrete transport vehicle scheduling method also includes the following steps:
[0070] S50: Get the map data to display a map in the interaction interface.
[0071] S60: The real-time position of each concrete transport vehicle is displayed on the map.
[0072] S70: The time of the working state, travel route, mileage, and its own production order, and expected production orders are expected to complete their own production orders.
[0073] Demonstrative, you can call an external map API (Application Program Interface, Application Interface), load the map, and display the real-time position of each concrete transport vehicle according to the GPS data of the concrete transport vehicle, or in the map The map is displayed on the map, the site location, and the production plan is displayed on the map, the target mixing station is drawn to the construction of the transportation route, the real-time position of the concrete trans...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com