Non-upper parallel connection steel truss girder composite beam and construction method
A construction method and combined beam technology, applied in bridges, bridge parts, bridge construction, etc., can solve the problems of no prestress, the difficulty of eliminating the risk of bridge deck cracking, and the inability to achieve full-section compression, etc., to achieve enhanced shear resistance capacity, save engineering cost, and increase the net height of the lower floor
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments It is a part of embodiments of the present invention, but not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
[0026] Such as figure 1 As shown, the embodiment of the present invention also provides a construction method for a combined beam without parallel steel truss girders, including steps:
[0027] S10: making the bridge deck section, and reserving the prestressed pipeline 5 and the shear nail grouting groove 8 in the bridge deck section;
[00...