Advanced water stop pouring construction method
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0024] Such as figure 1 As shown, the embodiment of the present invention includes the following steps:
[0025] S1, protective layer, waterproof, pit 3 construction;
[0026] S2, install the front half-width advanced water-stop mesh 6, and use the supporting steel bars to extend downwards to the pit 3 for fixation;
[0027] S3, fix the h-shaped fixed piece, the lower end of the h-shaped fixed piece extends into the pit 3, and install the sandwich foam board 7;
[0028] S4, pouring the first half of concrete;
[0029] S5, according to the first half of the advanced water stop, install the second half of the water stop mesh 6, the supporting steel bar and the h-shaped fixed piece;
[0030] S6, the half-width concrete after pouring.
[0031] Set the front 6 of the advanced water-stop mesh, first install the steel support.
[0032] The steel mesh sheets are firstly used as the lower layer and then as the upper layer.
[0033] In S1, the pouring tank is first cleaned, and th...