Intelligent wall leveling device for building construction
A technology for building construction and walls, which is applied in the field of intelligent wall leveling devices for building construction, and can solve problems such as huge equipment, inability to move to a suitable position according to needs, and cumbersome leveling process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] see figure 1 And 4-5, an intelligent wall leveling device for building construction, including a climbing mechanism 1 and a laser leveling device 2 installed above the climbing mechanism 1, the main driving power supply 11 is fixedly installed inside the climbing mechanism 1, and the main driving power supply 1 is fixedly installed on the outer side of the independent drive mechanism 12, the independent drive mechanism 12 is provided with six groups, the outer side of the independent drive mechanism 12 is fixedly connected with the first axis 13, the first axis 13 is connected with the shaft 14, the shaft 14 It is a flat rod body, the first axis 13 is provided at one end of the shaft 14 in contact with the independent driving mechanism 12, the other end of the shaft 14 is provided with a second axis 15, and the inner side of the second axis 15 is movably connected with a movable plate 16 A climbing rod 17 is connected to the side of the movable plate 16 away from the se...
Embodiment 2
[0036] see Figure 2-3And 6-8, an intelligent wall leveling device for building construction, the inside of the climbing rod 17 is provided with a circuit induction mechanism 3, the inside of the circuit induction mechanism 3 is fixedly installed with a power source 31 at the top, and the outside of the power source 31 Connected with an electromagnetic wire 32, the end of the electromagnetic wire 32 away from the power source 31 is provided with a solenoid valve 33, the inside of the solenoid valve 33 is provided with an electromagnetic coil 34, and the bottom of the electromagnetic coil 34 is connected with a ground terminal 35, and the bottom of the ground terminal 35, and A grounding block 36 is movably connected below the climbing pole 17 .
[0037] When the present invention climbs, the builders simultaneously build up the body of wall gradually, and the climbing mechanism 1 drives the present invention to climb continuously. At this time, six groups of climbing rods 17 a...
Embodiment 3
[0039] see Figure 1-8 , an intelligent wall leveling device for building construction, comprising a climbing mechanism 1 and a laser leveling device 2 installed above the climbing mechanism 1, a main driving power supply 11 is fixedly installed inside the climbing mechanism 1, and the outside of the main driving power supply 11 is fixed An independent driving mechanism 12 is installed, and the independent driving mechanism 12 is provided with six groups. The outer side of the independent driving mechanism 12 is fixedly connected with a first axis 13, and the first axis 13 is connected with a shaft 14. The shaft 14 is a flat rod body. The first shaft 13 is set at one end where the shaft 14 contacts the independent drive mechanism 12, the other end of the shaft 14 is provided with a second shaft 15, and the inner side of the second shaft 15 is movably connected with a movable plate 16, and the movable plate 16 The side far away from the second axis 15 is connected with climbing...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com