Dynamic Scheduling Method of Ground Lock Station Considering Art Pre- and Post-buffer

A technology of dynamic scheduling and buffer zone, applied in the field of port facilities, can solve the problems of reducing port operation efficiency, congestion of quay crane and lock station operation area, increase of time cost, etc., so as to improve equipment utilization rate, ensure operation balance, improve The effect of work efficiency

Active Publication Date: 2022-07-01
TIANJIN PORT SECOND CONTAINER TERMINAL CO LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In the existing container ports, the scheduling schemes of the lock station and the front and rear buffer zones are relatively fixed, and rely heavily on a single scheduling strategy, which often leads to low utilization of the lock station and buffer zone, and congestion in the quayside crane and lock station operation area. Seriously reduce the efficiency of port operations
At the same time, dynamic changes in equipment status are not considered in the scheduling strategy, and only a single fixed scheduling plan is followed, resulting in unsatisfactory scheduling results and ultimately resulting in low port efficiency.
[0003] As the loading and unloading workload increases, the time cost of traditional scheduling schemes also increases accordingly

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Dynamic Scheduling Method of Ground Lock Station Considering Art Pre- and Post-buffer
  • Dynamic Scheduling Method of Ground Lock Station Considering Art Pre- and Post-buffer
  • Dynamic Scheduling Method of Ground Lock Station Considering Art Pre- and Post-buffer

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0034] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments.

[0035] The embodiment of the present invention proposes a strategy of dynamic allocation of lock stations and buffers. According to the dynamic changes of each device, the ART enters the lock station and the buffer zone to be scheduled. The many-to-many allocation strategy of lock stations and quay cranes is adopted to coordinate the front buffer zone and the back buffer zone. The allocation of buffer zones improves the utilization rate of lock stations and quay cranes, and reduces the congestion of lock stations and quay crane operation lanes.

[0036] like figure 1 As shown in the figure, the ground locking station is located under the h...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a dynamic scheduling method for the ground locking station considering the ART front and rear buffers. According to the dynamic changes of the lock station and the buffer zone, the ART enters the lock station and the buffer zone when unloading the ship and entering the lock station and the buffer zone respectively when loading the ship. Scheduling: When unloading, according to the first-come, first-served and nearest allocation strategy, the ART is allocated a lock station; when loading, according to the operation efficiency of the lock station, the estimated time of the ART arriving at the quay crane, the logical relationship of container loading, the real-time position of the ART, The distance between the front buffer zone and the ART, and the estimated remaining travel time between the lock station and the front buffer zone. Allocate the lock station and the front buffer zone for the ART. At the same time, when the system receives the completion information of the ART unlocking operation of the ship loaded in the lock station, it will automatically control the unlocking operation. The completed ART goes into the free back buffer. The invention can improve the utilization rate of the lock station and the quay crane, and relieve the congestion phenomenon of the lock station and the quay crane operation lane.

Description

technical field [0001] The invention belongs to the technical field of port facilities, and in particular relates to a ground lock station dynamic scheduling method considering ART pre- and post-buffering. Background technique [0002] In recent years, the port industry, especially the port industry involving container transportation, has continuously improved the efficiency and intelligence of equipment scheduling. However, in the existing container ports, the scheduling scheme of the lock station and the front and rear buffers is relatively fixed, and it relies heavily on a single scheduling strategy, which often leads to low utilization of the lock station and buffer area, and congestion in the quay crane and the lock station operation area. Seriously reduce the efficiency of port operations. At the same time, the dynamic change of equipment status is not considered in the dispatching strategy, and only a single fixed dispatching scheme result is followed, resulting in u...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): G06Q10/06G06Q10/08
Inventor 焦广军杨荣高延辉武彬张凯张朋蒋天丽谢锦男冯淼管考举田博文
Owner TIANJIN PORT SECOND CONTAINER TERMINAL CO LTD